A communication transmitted from Louis A. DePasquale, City Manager, relative to a request for approval to seek authorization from the Massachusetts Office of the Inspector General (the “IG”) for the City to use the Construction Manager at Risk (“CMaR”) procurement and construction method (the “CMaR Method”) in connection with the Fire Department Headquarters Project
Procedures relative to receiving a
Notice to Proceed to use
Construction Management at-Risk
Services
OFFICE OF THE INSPECTOR GENERAL
C O M M O N W E A L T H O F M A S S A C H U S E T T S
O N E A S H B U R T O N P L A C E , R O O M 1 3 1 1
B O S T O N , M A 0 2 1 0 8 | ( 6 1 7 ) 7 2 7 - 9 1 4 0 | W W W . M A S S . G O V / I G
APRIL 2021
GLENN A. CUNHA
I N S P E C T O R G E N E R A L
This page is intentionally left blank.
i
TABLE OF CONTENTS
Overview of the CM at-Risk Application Process .......................................................................................... 1
Schedule ........................................................................................................................................................ 3
Application .................................................................................................................................................... 5
I.
General Information ..................................................................................................................... 5
II.
Awarding Authority Authorization Information ........................................................................... 7
III.
Awarding Authority Capacity Information .................................................................................... 7
IV.
Awarding Authority Plans and Procedures ................................................................................... 8
V.
Certification ................................................................................................................................... 9
Evaluation Process ...................................................................................................................................... 10
Certificate of Authority to use CM at-Risk Delivery Method
ii
This page is intentionally left blank.
1
OVERVIEW OF THE CM AT-RISK APPLICATION PROCESS
Prior to using the construction management at-risk (CM at-risk) delivery method to procure a
contract for the construction, reconstruction, installation, demolition, maintenance or repair of any
building estimated to cost $5 million or more, an awarding authority must obtain a Notice to Proceed to
use the CM at-risk delivery method from the Office of the Inspector General (OIG).
The OIG has developed this CM at-risk application to be completed on a project specific basis. The
application process will be important to awarding authorities in assessing the qualifications and
commitments that are necessary to the process to ensure construction of a high-quality, cost-effective
public building project. Before submitting an application, the public agency must assign or hire an owner's
project manager and procure the services of a designer. [M.G.L. c. 149A, § 3]
Under Section 4 of Chapter 149A of the Massachusetts General Laws, the OIG will issue a Notice
to Proceed when the public agency has demonstrated that:
•
The public agency has authorization from its governing body to enter into a contract with a
construction management at-risk firm. The authorization shall include the results of any public
vote if applicable.
•
The public agency has the capacity, a plan and procedures in place and approved of by the
governing body, where appropriate, to effectively procure and manage construction management
at-risk services for the specific project and has retained the services of a qualified owner's project
manager.
•
The public agency has in place procedures to ensure fairness in competition, evaluation and
reporting of results at every stage in the procurement process.
•
The building project has an estimated construction value of $5 million or more.
•
The public agency has determined that the use of construction management at-risk services is
appropriate for the building project and states in writing the reasons for the determination.
The OIG will review an awarding authority’s complete application and within 60 days from the
date a completed application is received will determine whether the awarding authority meets the
requirements necessary to obtain a Notice to Proceed.
Pursuant to M.G.L. c. 149A, if the OIG declines to issue a Notice to Proceed to an awarding
authority, the OIG shall provide in writing to the awarding authority the reason(s) for the decision. An
awarding authority not receiving a Notice to Proceed may resubmit its application upon correcting or
responding to the reason(s) for denial provided to the awarding authority by the OIG. The OIG shall make
a timely review of the resubmitted application and, if the awarding authority meets the requirements, the
OIG will issue a Notice to Proceed.
The OIG shall decline to issue a Notice to Proceed to an awarding authority that has failed to
provide complete and accurate answers to all questions in the application and all other information and
2
documentation required by the OIG. Providing false, misleading or incomplete information will be
considered grounds for denial.
Please submit an electronic copy of the application to IGO-Chapter-149A@mass.gov. We prefer
an electronic copy, however a hard copy may be submitted to the following address. Please do not use
any bindings or tabs when submitting a hard copy.
Office of the Inspector General
One Ashburton Place, Room 1311
Boston, MA 02108
If you have any questions regarding the application process, contact Mary Kolesar at 617-722-
8809 or Kerri-Anne Hollingshead at [phone removed] or by e-mail at IGO-Chapter-149A@mass.gov.
3
SCHEDULE
I.
Timetable for Review
The OIG will review an awarding authority’s complete application and within 60 days from the
date a completed application is received will determine whether the awarding authority meets the
requirements necessary to obtain a Notice to Proceed.
Event
OIG Task
Day 1
Awarding Authority submits application
to OIG
Date and timestamp application
Days 1-15
OIG contacts applicant acknowledging
receipt of application
Review application
Days 1-60
OIG determines whether additional
information is necessary and if so,
requests awarding authority to send
information
Request more information, if
necessary
Days 1-60
OIG reviews application to determine
whether awarding authority meets
requirements and will be issued a Notice
to Proceed
Analyze credentials based on
evaluation criteria
Days 1-60
OIG sends Notice to Proceed or Denial of
Notice to Proceed
Complete review and issue
determination
4
This page is intentionally left blank.
5
APPLICATION
Please submit one electronic application including copies of the signature pages, to the CM at-risk
mailbox: IGO-Chapter-149A@mass.gov. A paper copy may also be submitted to the OIG, but is not
required. To assist in the evaluation process, please submit and identify information and documents with
the item numbers on this application form.
I.
General Information
1.
Awarding Authority City of Cambridge
a. Awarding Authority Person in Charge of Project Assistant City Manager, David Kale
b. Awarding Authority Address Cambridge City Hall, 795 Massachusetts Avenue, Cambridge
MA 02139
c. Phone number of Awarding Authority Person in Charge of Project [phone removed]
d. E-mail
address
of
Awarding
Authority
Person
in
Charge
of
Project
dkale@cambridgema.gov
2.
Owner’s Project Manager (OPM) assigned or hired Brendon M. Roy
a. Phone number for OPM [phone removed]
b. E-mail address for OPM broy@cambridgema.gov
3.
Design Firm The Galante Architectural Studio
a. Principal Designer in Charge of Project Ted Galante
b. Phone number of Principal Designer [phone removed]
c. E-mail address of Designer [email removed]
4.
Narrative description and brief history of the project:
This project involves the renovation of the Cambridge Fire Department Headquarters (Fire
HQ) building, which is one of eight firehouses serving the City of Cambridge. Located at 491
Broadway, it was completed in 1933 and is listed as historically significant requiring
Cambridge Historical Commission review and Massachusetts Historical Commission
approval for this project. It is 30,389 square feet and supports both Fire Headquarters
Administration and Operations functions, as well as serves as a hub for the City’s fiber optic
communications network, and a backup Emergency Communications Center.
489 Broadway is the former site of Emergency Communications and is attached to 491
Broadway, providing the accessible entrance to the upper floors of 491 Broadway, and will
become programmed space for Fire HQ.
A preliminary site assessment of Fire HQ was conducted in 2016 by the Department of
Public Works (DPW), followed by a feasibility study completed in August 2020, which
6
revealed the complexity and challenges of renovating this historic public safety building on a
small urban site, while meeting the City’s ambitious sustainability goals and requirements.
The project scope includes a net zero emissions (all electric), LEED Gold renovation
including, but not limited to, interior, envelope, site, utility, communications, and fueling
station upgrades, lowering of the apparatus bay slab to accommodate modern firefighting
apparatus, as well as provide a solar photovoltaic array, ground source heat pumps, and
electric vehicle supply equipment.
Fire Headquarters is a 24/7/365 facility and houses Engine 1, Ladder 1 and Rescue 1,
Cambridge Fire Prevention and Permitting Office, a satellite Technical Services Office, and
hosts the backup citywide emergency radio and 911 communications. Careful coordination
of this project will be necessary to ensure the transition of existing communications to a
more resilient space in this facility, and allow for future expansion.
Prior to alterations to this building, construction of an offsite temporary facility for Fire
Operations will be required under this contract, as well as relocation of Fire Administration
and Permitting to a leased space.
a. estimated square feet 30,389
b. program type Public Safety
c. building type Brick Veneer, Wood & Steel frame, Slate roof.
5.
Project schedule elements, including, but not limited to:
a. Feasibility study completion date (if any) August 2020
b. Owner’s Project Manager contract execution date (if not an employee) City of
Cambridge employs an MCPPO certified OPM
c. Designer contract execution date December 2019
d. Projected procurement milestone dates, including but not limited to the following
items:
i. Request for prequalification issuance July 2022
ii. Request for proposals issuance August 2022
iii. CM at-risk firm contract execution date September 2022
iv. Other . . . __________
e. Projected completion date (use and/or occupancy) Winter 2025
6.
Submit an estimated total project budget, including but not limited to line items for the
following items: See Attachment “FDHQ Preliminary Budget Estimate April 2022”
a. Owner’s Project Manager contract amount (if not an employee) N/A
b. Designer contract amount 3,581,730.00
7
c. Estimated construction cost $47M
d. Other costs __________
e. Identify the source of the estimated project budget and estimated construction costs.
The City of Cambridge, City Council has appropriated initial design and construction
funding, and will appropriate additional design and construction funds for this
project as appropriate. The source of preliminary estimates is a combination of those
delivered by our architectural design team as well as historic data used by the OPM
team based on current CM at Risk projects. The construction costs have been
checked against and compared to similar construction activities projected to occur.
The soft costs are based on the past eight projects the same OPM team has been
involved with for the City of Cambridge.
II.
Awarding Authority Authorization Information
7.
Submit the attached certification form (see last page) regarding the authorization from the
awarding authority’s governing body that the awarding authority may enter into a contract
with a construction management at-risk firm, including the date of authorization. Submit
copies of any public vote if applicable. See “Certification of Authority Page 12”
8.
Submit the name(s) and title(s) of the individuals authorized to sign the CM at-risk contract
on behalf of the awarding authority. City Manager Louis A. DePasquale
9.
Submit written evidence of the approval of the governing body of the project plan and
procedures, if applicable. See attachment “City Council Vote dated May XX, 2022
10.
Submit the written determination by the awarding authority that the use of CM at-risk
services is appropriate for the building project and the reasons for the determination. See
attachment “Memorandum from City Manager to City Council dated May XX, 2022
III.
Awarding Authority Capacity Information
11.
Provide an organizational chart of the project organization showing the roles and
responsibilities of each individual or entity participating on the project, including
contractors. See “Attachment A”
12.
Provide the name, affiliation, and contact information for all key members of the project
team. List relevant qualifications and experience, including any public project experience
and any CM at-risk experience (public or private) on project(s) of similar size and complexity
or on any other projects, for:
a. the individual/s within the awarding authority that will make project decisions for the
awarding authority and that will supervise the Owner’s Project Manager, See
“Attachment A”
8
b. the Owner’s Project Manager (OPM),1 See “Attachment A”
c. the Designer,2 and See “Attachment A”
d. any other members of the project team or special consultants to be used to support
the project (e.g., counsel, accountant, financial advisor), if any. See “Attachment A”
13.
Submit a copy of the scope of services portion of the a) OPM contract and b) designer’s
contract. If the OPM is an employee, submit the individual’s title, job description and scope
of work related to the CM at-risk project. See “Attachment A”
[Note: You do not need to send in copies of the scopes of services if the project is a
school building project receiving assistance from the Massachusetts School Building
Authority (MSBA) and the OPM and Designer will be signing the MSBA contracts for
CM at-risk services in their entirety with no changes. However, submit a copy of the
signed signatory pages.]
IV.
Awarding Authority Plans and Procedures
The OIG reviews the awarding authority’s plan and procedures3 for procuring and managing the
CM at-risk services to ascertain whether the awarding authority has in place procedures, in accordance
with M.G.L. c. 149A, to ensure fairness in competition, evaluation and reporting of results at every stage
in the procurement process. Therefore, provide information regarding each of the following components
of a CM at-risk project:
14a.
The awarding authority’s plan and procedures for conducting the two-phase selection
process for hiring a construction manager at-risk firm and the methods that will be used
to ensure fairness in competition, evaluation and reporting of results at every stage in
the procurement. See “Attachment A”
14b.
The awarding authority’s plan and procedures for developing the cost-plus not to
exceed guaranteed maximum price form of contract. Include information on
negotiating the contract, including establishing the general condition items, CM at-risk
fee, cost of the work and other contract components. Include information on what level
of design development the awarding authority plans on establishing the GMP,
contingency and other components of the final contract amendment. See
1 M.G.L. c. 149A, § 3(a) states that “Before procuring the services of a designer … and prior to submitting an application to use
the construction management at-risk delivery method … the awarding authority shall procure or otherwise employ the services
of an owner's project manager pursuant to section 44A 1/2 of chapter 149. The owner's project manager may assist the awarding
authority in the procurement of the designer.“
2 M.G.L. c. 149A, § 3(b) states that “Before submitting an application to use the construction management at-risk delivery method
… the awarding authority shall procure the services of a designer for the building project. In procuring the services of a designer,
the awarding authority shall do so in a manner consistent with sections 38A ½ to 39O, inclusive, of chapter 7 (now sections 44-
58, inclusive, of chapter 7C). The designer procured by the awarding authority shall be independent of the owner's project
manager and the construction management at-risk firm.”
3 The plan and procedures must be approved by the governing body, where appropriate. [M.G.L. c. 149A, § 4(a)(2)].
9
“Attachment A”
14c.
The awarding authority’s plan and procedures for conducting the two-phase selection
process for obtaining trade contractors and the methods that will be used to ensure
fairness in competition, evaluation and reporting of results at every stage in the
procurement. See “Attachment A”
14d.
The awarding authority’s plan and procedures for obtaining subcontractors [M.G.L. c.
149A, § 8(j)] and the methods that will be used to ensure fairness in competition,
evaluation and reporting of results at every stage in the procurement. See
“Attachment A”
14e.
The awarding authority’s plan and procedures relative to administering and
coordinating the project and maintaining project communications. See “Attachment
A”
14f.
The awarding authority’s plan and procedures relative to monitoring and auditing all
project costs. See “Attachment A”
Do not submit requests for qualifications (RFQs), requests for proposals (RFPs), draft contracts, or
other such documents related to the CM at-risk delivery method procurement.
V.
Certification
The undersigned hereby certifies under the pains and penalties of perjury that all answers and all
information contained in this application are, to the best of my knowledge, true and correct.
_____________________________
_______________________________
Signature
Date
_____________________________
_______________________________
Title
Awarding Authority
10
EVALUATION PROCESS
The OIG will review the information submitted by the awarding authority and assess whether the
plan and procedures provide an adequate framework for procuring and managing a CM at-risk delivery
method project. The following criteria will be used in making a determination whether to issue a Notice
to Proceed.
•
Is the estimated construction cost $5 million or more?
•
Did the awarding authority receive approval from the appropriate governing body?4
•
Did the awarding authority’s governing body approve the plan and procedures?
•
Are the awarding authority’s goals and objectives for using the construction manager at-risk
method reasonable and designed to maximize competition?
•
Has the awarding authority established an experienced and effective project organization
structure, including an owner representative as a point of contact, an owner’s project
manager, and a designer?
•
Is the decision–making authority clear?
•
Do any project team members have relevant CM at-risk experience for the size and scope of
the project?
•
Does the plan and do the procedures demonstrate an appropriate assessment of the owner’s
tasks and responsibilities associated with a CM at-risk contract, including all aspects of
coordination and administration of the CM at-risk delivery method?
•
Does the plan and do the procedures provide an adequate framework for conducting the two-
phase selection process for a construction manager at-risk firm and clearly delineate the
methods that will be used to ensure fairness in competition, evaluation, and reporting of
results at every stage in the procurement, and otherwise comply with all statutory
requirements?
•
Does the plan and do the procedures provide an adequate framework for negotiating the
cost-plus not to exceed guaranteed maximum price form of contract?
•
Does the plan and do the procedures provide an adequate framework for conducting the two-
phase selection process for trade contractors and clearly delineate the methods that will be
used to ensure fairness in competition, evaluation, and reporting of results at every stage in
the procurement, and otherwise comply with all statutory requirements?
•
Does the plan and do the procedures provide an adequate framework for obtaining
subcontractor contracts and clearly delineate the methods that will be used to ensure fairness
in competition, evaluation, and reporting of results at every stage in the procurement?
•
Does the plan and do the procedures provide an adequate framework for administering and
coordinating the project and maintaining project communications?
4 The “appropriate governing body” varies, depending on an awarding authority’s charter and other
factors.
11
•
Does the plan and do the procedures provide an adequate framework for auditing and
monitoring all project costs?
•
Is the schedule realistic?
Although the OIG will rely primarily on the information presented in the application to make its
determination, the OIG reserves the right to obtain additional information and to verify information.
CERTIFICATE OF AUTHORITY TO USE CM AT -RISK DELIVERY METHOD
I, _______________________________, [legal counsel for the governing body as identified below] do
hereby certify to the Office of the Inspector General of the Commonwealth of Massachusetts, in accordance
with M.G.L. c. 149A, § 4(a)(1), regarding using construction management at risk services for the following
project_______________________________________ (“Project”), as follows:
(1) That ___________________________ [name of political subdivision] is a public
agency as defined in M.G.L. c. 149, § 44A(1), is duly organized and existing under
the laws of the Commonwealth of Massachusetts, and has received the necessary
authority and power from _____________________[its city council, town meeting
or other governing body] to enter into a contract with a construction management
at risk firm and to perform all its obligations in connection with the Project.
(2) That the public vote of the governing body, attached hereto (if applicable) was
duly adopted and is currently in effect.
_____________________________
Signature
_____________________________
[SEAL]
Title
_____________________________
Date