Search ▸ Agenda item attachment
A communication transmitted from Yi-An Huang, City Manager, relative to Awaiting Report Item Number AR #24-27, regarding a list of current zoning initiatives and a timeline for completion
C I T Y O F C A M B R I D G E
Community Development Department
IRAM FAROOQ
Assistant City Manager for
Community Development
SANDRA CLARKE
Deputy Director
Chief of Administration
MELISSA PETERS
Chief of Planning Strategy
To:
Yi-An Huang, City Manager
From:
Iram Farooq, Assistant City Manager for Community Development
Date:
June 20, 2024
Subject:
Awaiting Report #24-27 dated June 3, 2024 re. providing a list of current
zoning initiatives and a timeline for completion
Based on discussions at the City Council and various Council Committees over the last few
months, CDD and Law Department staff are prioritizing the following zoning initiatives in
our workplans.
Multifamily Zoning: Work on rezoning to facilitate multifamily development is
underway at the Housing Committee and includes eliminating exclusionary zoning and
expanding capacity for multifamily housing development citywide. In terms of timeline,
we are prioritizing this work since it will create the new baseline that will need to be
factored into other area specific rezoning work such as the Mass Ave Planning Study and
the Central Square Rezoning effort, both of which are already in process.
Shared Parking: Amendments to accessory parking provisions in the Zoning
Ordinance to mitigate the loss of on street parking resulting from the installation of
separated bicycle facilities as the Cycling Safety Ordinance (CSO) is implemented. Law
department staff will also work with CDD’s transportation planning staff to work on
companion changes to the Parking and Transportation Demand Management (PTDM)
Ordinance. In terms of timeline, this work is being prioritized so that changes are in
place before further implementation of the CSO.
Central Square Rezoning: Guided by community goals identified in prior planning
efforts, we initiated a community process in late May related to rezoning Central Square
with a focus on increasing housing, creating public spaces to build community, and
supporting our diverse retail, cultural, and non-profit community.
Cambridge Street Rezoning: Draft zoning text was drafted based on the
recommendations of the Our Cambridge Street planning process. Work that is currently
underway on multifamily zoning is likely to impact these recommendations and the
proposed zoning may need to be modified. We will make changes to the draft, as
needed, and bring forward this rezoning after the adoption of citywide multifamily
zoning.
Anticipated timelines for these items are shown below. The adoption timeframes are
impacted greatly by things that are not in staff control and are, therefore, shown as
dashed lines. These include logistical items such as the timing of hearings, number of
hearings needed for deliberation, and complexity of discussions at Ordinance
Committee and the Planning Board. They also include substantive items such as if the
2
City Council chooses to expand the scope of the zoning or if issues come up during the
course of deliberations that necessitate further analysis or drafting amendments.
Further, these timelines can be impacted by new items that require immediate action
such zoning petitions from citizens, developers/property owners, or the City Council and
other time-sensitive requests.
Fig. 1 ANTICIPATED ZONING TIMELINE FOR PRIORITY PROJECTS
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Multifamily
Shared
Parking
Central
Square
Cambridge
St
Zoning Development
Petition filing
Consideration at Ordinance Comm
& Planning Board
Zoning adoption
Stakeholder Engagement:
Community Process and RFI
During this time, staff and the City Council will also be processing the Griffin Sheperd et
al petition. Any new zoning petitions that are filed may extend some or all of these
timelines.
We also want to take this opportunity to mention upcoming zoning work in 2025. The
Mass Ave Planning Study that is currently underway will result in zoning
recommendations, that we expect to work on in 2025. Additionally, the Alewife District
Plan had contemplated changes to the Shopping Center and Triangle Areas. These were
not developed fully with the community given the time-sensitivity of advancing the
Quadrangle zoning. Developing a vision and zoning for this area will gain importance as
the MBTA anticipates initiating planning for potential redevelopment of the Alewife
parking garage.