Search ▸ Agenda item attachment
A communication transmitted from Yi-An Huang, City Manager, relative to Awaiting Report Item Number 24-69 regarding asbestos concerns with the MBTA's Alewife construction
January 29, 2025
To the Honorable, the City Council:
In response to Awaiting Report 24-069, dated December 9, 2024, city staff from the Community
Development Department, the Department of Public Works and the Public Health Department
have provided the update below on the MBTA’s Red Line Hi-Rail Access Tunnel Project and on-
going coordination with the MBTA.
Red Line Hi-Rail Access Tunnel Project – Background
The Massachusetts Bay Transportation Authority (MBTA) is planning to construct an access
tunnel in the Alewife area to allow hi-rail work vehicles access to the Red Line Tunnel.
Currently, the closest access for these critical maintenance vehicles is at Charles/MGH station.
The new Hi-Rail Access Tunnel will enable shorter and less frequent Red Line shutdowns, faster
commutes, and support the MBTA’s continued efforts to bring the subway system to a state of
good repair. The MBTA is currently in design of the $32.9M project, with construction
anticipated to start in June 2026 and finish in March 2028.
Red Line Hi-Rail Access Tunnel Project – State Environmental Review Process
The project site was used for manufacturing between 1919 and 1983, and is known to have
contaminated soil, including asbestos. Based on this history, the MBTA is managing the
construction and handling of contaminated soils under the Massachusetts Department of
Environmental Protection (MassDEP) regulations, including a Release Abatement Measure
(RAM) Plan and a Non-Traditional Asbestos Abatement Work Plan (NTAAWP). In order to
identify the extent and type of contamination in the soils, the MBTA completed 64 soil borings
on a 15’ grid and analyzed 148 soil samples.
The testing identified asbestos fibers in 56 of 148 samples (37%). Of those 56 samples
containing asbestos fibers, 46 samples contained less than 1% asbestos and the highest was
1.92%. The asbestos fibers were identified in the top 6’ of soil, correlating with fill material.
Based on these samples, the RAM Plan is proposing to treat all of the top 6’ of material as
asbestos contaminated. The soil testing also identified areas with naphthalene contamination,
consistent with historic uses on the property.
The two slides below are from the MBTA’s September 29, 2024 community meeting and
highlight the areas that will be treated as containing asbestos (top 6’ of soil), the area with
naphthalene contamination, and summaries of the Excavation Plan and the RAM Plan.
The draft RAM plan for the excavation was released in August 2024. The MBTA had discussions
with local residents and the Alewife Study Group in September and October, and hosted a
public meeting on September 29, 2024. The comment period on the draft RAM plan closed on
December 8, 2024.
While the MBTA has not committed to following the Cambridge Asbestos Protection Ordinance,
Chapter 8.61, which was passed in 1999 due to concerns that the MassDEP oversight of soil
handling activities around asbestos contaminated soils was lacking and additional local
measures needed to be put in place to properly protect the community. Since that time,
MassDEP has increased their oversight and is currently completing a study of release sites
containing asbestos following the increased protocols. MassDEP has indicated to city staff that
the study results show that there were no recorded off-site releases based on substantial
perimeter monitoring data above any applicable threshold in any site so managed.
In addition to the increased MassDEP oversight, the MBTA have proposed several protocols
that surpass MassDEP requirements including a tighter testing grid, additional air monitoring
locations, and lower limits for the air monitoring. The MBTA have also indicated that they are
continuing to evaluate the use of tents with filtration or full tenting and venting, as the design
and bidding process progresses.
Status of MBTA Design and Coordination with City Staff
To further advocate that the MBTA comply with the Cambridge Asbestos Ordinance and
incorporate tenting and venting protocols, as requested in the Council Order, city staff met with
the MBTA and their consultants. The MBTA indicated that their tunnel plans are currently at
75%-design, so further changes are feasible before a final plan for construction and remediation
is submitted. They also indicated that they may not be able to commit to a final decision on
tenting and venting until the project is bid and the final RAM plan is submitted to MassDEP
towards the end of 2025 or early in 2026. Staff emphasized that there is significant public
interest in understanding what they intend to do before the full bidding and regulatory
timelines play out.
City staff will continue to meet with the MBTA for updates on their plans and procedures for
construction, including the request to follow the Asbestos Ordinance, and monitor the RAM
Plan process with DEP.
Very truly yours,
Yi-An Huang
City Manager