Search ▸ Agenda item attachment
A communication transmitted from Louis A. DePasquale, City Manager, relative to Awaiting Report Item Numbers 18-11 and 18-12, regarding the Cambridge Crossing sewer main on Gore Street
City of Cambridge
Department of Public Works
Owen O'Riordan, Commissioner
147 Hampshire Street
Cambridge, MA 02139
theworks@cambridgema.gov
Voice: [phone removed]
TDD: [phone removed]
September 24, 2018
To:
Louis DePasquale
City Manager
From: Katherine F. Watkins, City Engineer
Re:
Awaiting Reports 18-11 and 18-12, dated January 29, 2018
Gore Street
In response to the council orders regarding the Cambridge Crossing sewer main on Gore Street,
staff report the following:
GORE STREET SEWER CONSTRUCTION UPDATE:
Construction of a new city sewer main on Gore Street between Monsignor O’Brien Highway
and Medford Street in Somerville commenced in spring 2018. Construction started in
Somerville and is progressing to the east into Cambridge. The sewer installation is complete to
almost Lambert Street. Work will continue to the east towards Monsignor O’Brien Highway
this winter, as weather permits. The connection to the MWRA’s regional wastewater system in
Somerville is expected to occur in 2019 and the sewer main construction is expected to continue
into the 2019 construction season.
This past spring, Eversource began replacing the over 100 year old gas main on Gore Street.
Gas main replacement started near Monsignor O'Brien Highway and is proceeding west down
Gore Street towards the Somerville city line.
OPEN CUT CONSTRUCTION VS. TRENCHLESS TECHNOLOGY:
The new sewer main is approximately 8 to 15 feet deep and is being constructed using typical
open cut construction methods. Trenchless construction was proposed in the initial design, but
was determined to be more disruptive to the community.
While trenchless construction reduces the length of the excavation, significant excavation is still
required. Relatively large access pits, called launching and receiving pits are placed at either
end of construction zones where pipes will be installed. These pits are needed for the equipment
and materials used in the trenchless process. Trenchless construction on Gore Street would have
required two to three sets of access pits ranging in size from 8 to 10 feet wide by 15 to 25 feet
long and depths of over 15 feet. The size of these access pits would present significant
challenges on Gore Street due to the number of existing subsurface utilities and would be
disruptive to the neighborhood. Laydown areas for the launching pits for the long lengths of
fused pipe to be installed would have required significant removal of on-street parking. Sewer
manholes, which are required for operation and maintenance, are required approximately every
300 feet. These manholes would need to be constructed using open cut excavation and would
be 15 to 30 deep.
To reduce the depth of the construction, Divco West modified the design to include a sewer
pumping station at Cambridge Crossing, which allows the sewer main to be installed at a higher
elevation; reducing the excavation depths to 8 to 15 feet which is more typical for sewer
construction and can proceed using the traditional open cut excavation method.
CONSTRUCTION IMPACTS:
The DPW has been working with DivcoWest to coordinate design and construction activities
and reduce impacts to the community.
• DivcoWest engaged with a construction mitigation firm, CSL Consulting, to manage
construction notifications and updates, and to respond to concerns. CSL Consulting has
set up a project web site with updates and contact information
https://cxconstruction.info/ Residents can sign up for project updates through the web
site.
• DivcoWest and DPW co-hosted a public meeting in September 2017 to review the
project and construction impacts; and discuss mitigation efforts.
• Resident parking has been a key concern for Gore Street residents. The City has reduced
the fees for monthly parking in the City’s First Street Garage for residents impacted by
the construction and DivcoWest has committed to paying the fees. The information
below explains how to sign up for the parking and has been distributed to residents.
o The City is extending the wintertime $50 per month parking in the City’s First
Garage to year-round for residents of Gore Street. DivcoWest will pay the $50
monthly charge for residents of Gore Street, so monthly passes in the City’s First
Street Garage will be free of charge to Gore Street residents impacted by the
sewer construction. Please contact [email removed] or by phone at
[phone removed] to discuss parking options during construction.
• DivcoWest has worked closely with the City’s Inspectional Services Department to
identify any areas with rodent activity, coordinated with local businesses to improve
existing rodent control plans and baited sewers in the Gore Street area. Proactive rodent
management will continue throughout construction.
• DivcoWest has offered preconstruction surveys to all properties on Gore Street. The
notification process started in mid-January and all properties identified for
preconstruction surveys were notified by mid-February.
• DivcoWest held a meeting in the spring, 2018 to update impact residents on their
construction efforts.
• As part of the water main replacement, any lead water services will be replaced from the
water main to the meter, at no cost to the property owner.
• The design and construction of the surface reconstruction (paving, sidewalk, street trees,
etc.) will be paid for by DivcoWest, but managed by the City. The kick-off community
meeting for the surface design was held on June 19th and the second community meeting
will be held on November 1st from 7:00 – 8:30 pm at Millers River, 15 Lambert Street.