Search ▸ Agenda item attachment
A communication transmitted from Louis A. DePasquale, City Manager, relative to a request for approval to seek authorization from the Massachusetts Office of the Inspector General (the “IG”) for the City to use the Construction Manager at Risk (“CMaR”) procurement and construction method (the “CMaR Method”) in connection with the Tobin Montessori and Vassal Lane Upper Schools Project
Office of the Inspector
General
Commonwealth of Massachusetts
Glenn A. Cunha
Inspector General
Procedures relative to receiving a
Notice to Proceed to Use
Construction Management at Risk
Services
April 2013
Table of Contents
Introduction
............................................................................................................. 1
Schedule
............................................................................................................. 3
Application
............................................................................................................. 4
Evaluation Process ....................................................................................................... 9
Attachment: CERTIFICATION OF AUTHORITY TO USE THE
CONSTRUCTION MANAGEMENT AT RISK DELIVERY
METHOD
© Office of the Inspector General, Commonwealth of Massachusetts 2013. All rights reserved.
Massachusetts Office of the Inspector General
Address:
Room 1311
John McCormack State Office Building
One Ashburton Place
Boston, MA 02108
Contact Information:
(617) 727 - 9140
(617) 523 - 1205 (MCPPO Program)
(800) 322 - 1323 (Confidential 24-hour Hotline)
(617) 723 - 2334 (FAX)
(617) 722 - 8809 (CM at risk application)
www.mass.gov/ig
1
Introduction
Office of the Inspector General
Construction Management at Risk Application to Proceed
Prior to using the construction management at risk (CM at risk) delivery method to
procure a contract for the construction, reconstruction, installation, demolition,
maintenance, or repair of any building estimated to cost $5 million or more, an awarding
authority must obtain a Notice to Proceed to use the CM at risk delivery method from
the Office of the Inspector General (OIG).
The OIG has developed this CM at risk application to be completed on a project specific
basis. The application process will be important to awarding authorities in assessing
the qualifications and commitments that are necessary to the process to ensure
construction of a high-quality, cost-effective public building project.
Under M.G.L. c. 149A, §4, the OIG will issue a Notice to Proceed when the public
agency has demonstrated that:
a. The public agency has authorization from its governing body to enter into a
contract with a construction management at risk firm. The authorization shall
include the results of any public vote if applicable.
b. The public agency has the capacity, a plan and procedures in place and
approved of by the governing body, where appropriate, to effectively procure and
manage construction management at-risk services for the specific project and
has retained the services of a qualified owner's project manager.
c. The public agency has in place procedures to ensure fairness in competition,
evaluation and reporting of results at every stage in the procurement process.
d. The building project has an estimated construction value of $5,000,000 or more.
e. The public agency has determined that the use of construction management at
risk services is appropriate for the building project and states in writing the
reasons for the determination.
The OIG will review an awarding authority’s complete application and within 60 days
from the date a completed application is received will determine whether the awarding
authority meets the requirements necessary to obtain a Notice to Proceed.
Pursuant to M.G.L. c. 149A, if the OIG declines to issue a Notice to Proceed to an
awarding authority, the OIG shall provide in writing to the awarding authority the
reason(s) for the decision. An awarding authority not receiving a Notice to Proceed may
resubmit its application upon correcting or responding to the reason(s) for denial
provided to the awarding authority by the OIG. The OIG shall make a timely review of
2
the resubmitted application and, if the awarding authority meets the requirements, the
OIG will issue a Notice to Proceed.
The OIG shall decline to issue a Notice to proceed to an awarding authority that has
failed to provide complete and accurate answers to all questions in the application and
all other information and documentation required by the OIG. Providing false,
misleading, or incomplete information will be considered grounds for denial.
Applications must be submitted to: Office of the Inspector General, Room 1311, One
Ashburton Place, Boston, MA 02108.
If you have any questions regarding the application process, contact Mary Kolesar,
Senior Policy Analyst, Policy and Government Division, at [phone removed] or by e-mail at
[email removed].
3
Schedule
Event
Task
Day 1
Awarding Authority Submits Application to
Proceed (by mail) to:
Office of the Inspector General
One Ashburton Place, Room 1311
Boston, MA 02108
Date and time stamp
application
Day 1 – 15
1. OIG reviews application in a timely
manner.
2. OIG contacts applicant acknowledging
receipt of the application
Review application
Day 1-60
1. OIG determines whether additional
information is necessary and if so,
requests awarding authority to send
information
2. OIG reviews application to determine
whether awarding authority meets
requirements and will be issued a Notice
to Proceed
3. OIG sends Notice to Proceed or Denial of
Notice to Proceed
•
Verify information
•
Request more
information, if
necessary
•
Analyze credentials
based on evaluation
criteria
•
Complete review and
issue determination
4
Application
Please submit one original with signature pages and one copy of the following
information. Use additional sheets where necessary. To assist in the evaluation
process, please submit and identify information and documents with the item numbers
on this application form.
Part A: General Information
a. Awarding Authority City of Cambridge
b. Awarding Authority Person in Charge of Project Deputy City Manager,
Lisa Peterson
c. Awarding Authority Address City Hall, 795 Massachusetts Avenue,
Cambridge MA 02139
d. Phone number of Awarding Authority Person in Charge of Project
[phone removed]
e. Fax number of Awarding Authority Person in Charge of Project N/A
f. E-mail address of Awarding Authority Person in Charge of Project
lisap@cambridgema.gov
2. OPM name Michael J. Black
3. Designer name Perkins Eastman
Narrative description and brief history of the project: The City of Cambridge School
Department has implemented an Innovation Agenda to become district of JK-5
schools, with four upper school campuses that feed into the Cambridge Rindge &
Latin High School. The Tobin Montessori and Vassal Lane Upper Schools is the
third school building to be modernized to accept the Innovative Agenda
Programming Curriculum.
4. estimated square feet 250,000
a. program type: Educational, Community, Recreational
Office of the Inspector General
Construction Management at Risk Application to Proceed
5
b. building type: Concrete, steel and masonry
5. Project schedule elements, including, but not limited to:
a. Feasibility study completion date (if any) Fall 2019
b. Owner’s Project Manager contract execution date (if not an employee)
City of Cambridge employs an MCPPO certified OPM
c. Designer contract execution date February 2019
d. Projected procurement milestone dates, including but not limited to the
following items: Request for prequalification issuance, request for
proposals issuance, CM at risk firm contract execution date, other. .
Construction Manager at Risk, RFQ scheduled for June 2019,
estimated contract execution date July 2019
e. Projected completion date (use and/or occupancy) Summer 2024
f. Submit an estimated total project budget, including but not limited to line
items for the following items: See Attachment “Tobin Preliminary
Estimated – January 2019”
g. Owner’s Project Manager contract amount (if not an employee)
h. Designer contract amount Feasibility Study $1,500,000
i. Estimated construction cost $170 - $200M
j. Other costs
k. Identify the source of the estimated project budget and estimated
construction costs. The source of the preliminary estimate was the Dr.
Martin Luther King Jr. project, 100 Putnam Avenue, & the King
Open/Cambridge Street Upper School & Community Complex
project, 850 Cambridge Street, presently under construction, both
projects using CM at Risk delivery method. The soft costs are based
on the historic data from the ten projects the OPM has been
involved with for the City of Cambridge.
6. Submit the attached certification form (see last page) regarding the
authorization from the awarding authority’s governing body that the awarding
authority may enter into a contract with a construction management at risk
firm, including the date of authorization. Submit copies of any public vote if
applicable. See “Certification of Authority Page 12”
7. Submit the name(s) and title(s) of the individuals authorized to sign the CM
at risk contract on behalf of the awarding authority. City Manager Louis A.
DePasquale
8. Submit written evidence of the approval of the governing body of the project
plan and procedures, if applicable. See Attachment “City Council vote
dated April 1, 2019”
Office of the Inspector General
Construction Management at Risk Application to Proceed
6
9. Submit the written determination by the awarding authority that the use of CM
at risk services is appropriate for the building project and the reasons for the
determination. See Attachment “Memorandum from City Manager to City
Council dated April 1, 2019”
Part B. Awarding Authority Capacity Information
10. Provide an organizational chart of the project organization showing the roles
and responsibilities of each individual or entity participating on the project,
including contractors. See “Attachment A” and “Organizational Chart”
11. Provide the name, affiliation, and contact information for all key members of
the project team. List all relevant qualifications and experience, including
any public project experience and any CM at risk experience (public or
private) on project(s) of similar size and complexity or on any other projects,
for: See “Attachment A”
a. the individual/s within the awarding authority that will make project
decisions for the awarding authority and that will supervise the Owner’s
Project Manager, See “Attachment A”
b. the Owner’s Project Manager (OPM),1 “Attachment A”
c. the Designer,2 and See “Attachment A”
d. Any other members of the project team or special consultants to be used
to support the project (e.g., counsel, accountant, financial advisor), if any.
See “Attachment A”
12. Submit a copy of the scope of services portion of the a) OPM contract and b)
designer’s contract. If the OPM is an employee, submit the individual’s title,
job description, and scope of work related to the CM at risk project.
[Note: You do not need to send in copies of the scopes of services if the
project is a school building project receiving assistance from the
Massachusetts School Building Authority (MSBA) and the OPM and
Designer will be signing the MSBA contracts for CM at risk services in
1 M.G.L. c. 149A, § 3(a) states that “Before procuring the services of a designer … and prior to
submitting an application to use the construction management at risk delivery method … the
awarding authority shall procure or otherwise employ the services of an owner's project
manager pursuant to section 44A 1/2 of chapter 149. The owner's project manager may assist
the awarding authority in the procurement of the designer. “
2 M.G.L. c. 149A, § 3(b) states that “Before submitting an application to use the construction
management at risk delivery method … the awarding authority shall procure the services of a
designer for the building project. In procuring the services of a designer, the awarding authority
shall do so in a manner consistent with sections 38A ½ to 39O, inclusive, of chapter 7. The
designer procured by the awarding authority shall be independent of the owner's project
manager and the construction management at risk firm. “
Office of the Inspector General
Construction Management at Risk Application to Proceed
7
their entirety with no changes. However, submit a copy of the signed
signatory pages.] See “Attachment “A”
The OIG reviews the awarding authority’s plan and procedures3 for procuring and
managing the CM at risk services to ascertain whether the awarding authority has in
place procedures, in accordance with M.G.L. c. 149A, to ensure fairness in competition,
evaluation and reporting of results at every stage in the procurement process.
Therefore, provide information regarding each of the following components of a CM at
risk project:
14a. The awarding authority’s plan and procedures for acquiring appropriate
expertise to assist where the team may not have the necessary
experience to meet anticipated challenges. “Attachment A”
14b. The awarding authority’s plan and procedures for conducting the two-
phase selection process for hiring a construction manager at risk firm
and the methods that will be used to ensure fairness in competition,
evaluation, and reporting of results at every stage in the procurement.
See “Attachment A”
14c. The awarding authority’s plan and procedures for developing the cost-
plus not to exceed guaranteed maximum price form of contract. Include
information on negotiating the contract, including establishing the
general condition items, CM at risk fee, cost of the work, and other
contract components. Include information on what level of design
development the awarding authority plans on establishing the GMP,
contingency, and other components of the final contract amendment.
See “Attachment A”
14d. The awarding authority’s plan and procedures for conducting the two-
phase selection process for obtaining trade contractors and the methods
that will be used to ensure fairness in competition, evaluation, and
reporting of results at every stage in the procurement. See “Attachment
A”
14e. The
awarding
authority’s
plan
and
procedures
for
obtaining
subcontractors [M.G.L. c. 149A, § 8(j)] and the methods that will be used
to ensure fairness in competition, evaluation, and reporting of results at
every stage in the procurement. See “Attachment A”
14f. The awarding authority’s plan and procedures relative to administering
and coordinating the project and maintaining project communications.
See “Attachment A”
14g. The awarding authority’s plan and procedures relative to monitoring and
auditing all project costs. See “Attachment A”
3 The plan and procedures must be approved by the governing body, where appropriate.
[M.G.L. c. 149A, § 4(a)(2)]
Office of the Inspector General
Construction Management at Risk Application to Proceed
8
Do not submit requests for qualifications (RFQs), requests for proposals (RFPs), draft
contracts, or other such documents related to the CM at risk delivery method
procurement.
9
Evaluation Process
Office of the Inspector General’s Evaluation Process
The OIG will review the information submitted by the awarding authority and assess
whether the plan and procedures provide an adequate framework for procuring and
managing a CM at risk delivery method project. The following criteria will be used in
making a determination whether to issue a Notice to Proceed.
Is the estimated construction cost $5 million or more?
Did the awarding authority receive approval from the appropriate governing body?4
Did the awarding authority’s governing body approve the plan and procedures?
Are the awarding authority’s goals and objectives for using the construction manager
at risk method reasonable and designed to maximize competition?
Has the awarding authority established an experienced and effective project
organization structure, including an owner representative as a point of contact, an
owner’s project manager, and a designer?
Is the decision–making authority clear?
Do any project team members have relevant CM at risk experience for the size and
scope of the project?
Does the plan and do the procedures demonstrate an appropriate assessment of the
owner’s tasks and responsibilities associated with a CM at risk contract, including all
aspects of coordination and administration of the CM at risk delivery method?
Has the awarding authority established a plan for acquiring appropriate expertise to
assist where the team may not have the necessary experience to meet anticipated
challenges?
Does the plan and do the procedures provide an adequate framework for conducting
the two-phase selection process for a construction manager at risk firm and clearly
delineate the methods that will be used to ensure fairness in competition, evaluation,
and reporting of results at every stage in the procurement, and otherwise comply with all
statutory requirements?
Does the plan and do the procedures provide an adequate framework for negotiating
the cost-plus not to exceed guaranteed maximum price form of contract?
Does the plan and do the procedures provide an adequate framework for conducting
the two-phase selection process for trade contractors and clearly delineate the methods
that will be used to ensure fairness in competition, evaluation, and reporting of results at
every stage in the procurement, and otherwise comply with all statutory requirements?
4 The “appropriate governing body” varies, depending on an awarding authority’s charter and
other factors.
Office of the Inspector General
Construction Management at Risk Application to Proceed
10
Does the plan and do the procedures provide an adequate framework for obtaining
subcontractor contracts and clearly delineate the methods that will be used to ensure
fairness in competition, evaluation, and reporting of results at every stage in the
procurement?
Does the plan and do the procedures provide an adequate framework for
administering and coordinating the project and maintaining project communications?
Does the plan and do the procedures provide an adequate framework for auditing
and monitoring all project costs?
Is the schedule realistic?
Although the OIG will rely primarily on the information presented in the application to
make its determination, the OIG reserves the right to obtain additional information and
to verify information.
Certification
The undersigned hereby certifies under the pains and penalties of perjury that all
answers and all information contained in this application is, to the best of my
knowledge, true and correct.
_____________________________
_______________________________
Signature
Date
_____________________________
_______________________________
Title
Awarding Authority
Office of the Inspector General
Construction Management at Risk Application to Proceed
11
If the OIG’s review results in a determination that an awarding authority appears to lack
sufficient capacity to effectively procure and manage a CM at risk construction project,
the OIG will provide in writing to the awarding authority the reason(s) for the
determination. An awarding authority may resubmit a detailed application, correcting or
responding to the reason(s) identified by the OIG. The OIG shall review the resubmitted
application.
If the OIG’s review results in a determination that an awarding authority has
demonstrated sufficient capacity to effectively procure and manage a CM at risk
construction project, the OIG shall issue a Notice to Proceed. Along with the Notice to
Proceed, the OIG will provide a summary report form to be completed by the awarding
authority within 70 days from completion of the building project or termination of the
contractor on the CM at risk building project.
The OIG shall decline to issue a Notice to proceed to an awarding authority that has
failed to provide complete and accurate answers to all questions in the application and
all other information and documentation required by the OIG. Providing false,
misleading, or incomplete information will be considered grounds for denial.
12
CERTIFICATION OF AUTHORITY TO USE THE CONSTRUCTION
MANAGEMENT AT RISK DELIVERY METHOD
I, Nancy E. Glowa, City Solicitor for the City of Cambridge do hereby certify to the Office
of the Inspector General of the Commonwealth of Massachusetts, in accordance with
M.G.L. c. 149A, § 4(a)(1), regarding using construction management at risk services for
the following project: Tobin Montessori and Vassal Lane Upper Schools Project
(“Project”), as follows:
(1) That the City of Cambridge is a public agency as defined in
M.G.L. c. 149, § 44A (1), is duly organized and existing under the
laws of the Commonwealth of Massachusetts, and has received the
necessary authority and power from City Council to enter into a
contract with a construction management at risk firm and to perform
all its obligations in connection with the Project.
(2) That the public vote of the governing body, attached hereto (if
applicable) was duly adopted and is currently in effect.
_____________________________
Signature
_____________________________
[SEAL]
Title
_____________________________
Date