Search ▸ Agenda item attachment
A communication transmitted from Louis A. DePasquale, City Manager, relative to Awaiting Report Item Number 19-81, regarding the new traffic signals at the intersection of Broadway and Ellery Street
MEMORANDUM
To:
Louis A. DePasquale, City Manager
From:
Joseph E. Barr, Director
Date:
July 29, 2019
Subject:
Awaiting Report 19-81 – Report on delays in activating the newly
constructed traffic signal on Broadway at Ellery Street
This memo is in response to Order 4 from the June 17, 2019 City Council
Meeting (Awaiting Report 19-81) requesting a review and chronology of the
installation of the new traffic signal at the intersection of Broadway and Ellery
Street.
In September of 2018, to prepare for the (then) upcoming installation of new
traffic signals at Broadway and Ellery Street, we applied for approval from the
Pole & Conduit Commission to install the necessary hardware and conduit. We
received a Grant of Location from the Pole & Conduit Commission on
September 20th which allowed us (through our contractor) to install the conduit
necessary for signalization, including the electric service conduit needed to
energize the signals.
Construction of the signal commenced on December 1, 2018 following the
construction bidding procurement. The contractor awarded this work, Dagle
Electrical Construction Corp, sent the Department of Public Works a notification
letter of the construction start date. The foreperson from Dagle also began to
coordinate with a representative of Eversource Electric about establishing a
new service connection (to energize the signals). Preliminary installation of
traffic conduit and traffic light foundations took place in mid-December.
Dagle completed the majority of the signal installation work and applied for an
Electrical Permit with the Inspectional Services Department (ISD) in early
March. By the end of March, ISD electricians inspected and approved the
service connection. Directly following the inspection on April 2, 2019, Dagle
reached out to Eversource about energizing the signals by providing an
electrical connection. Eversource requested payment on April 15 for the service
connection and Dagle sent out a check the same week for payment. Dagle and
the City followed-up through emails and phone calls to attempt to get
Eversource to provide power to the signals, but Eversource was unable to
provide an exact schedule for the connection work.
City staff communicated with Eversource multiple times over the 10-week
period between the completion of the traffic signal installation and the eventual
activation to communicate the critical safety concerns associated with the
delays in activation. Both City and Dagle staff emailed Eversource contacts on
eight separate occasions, while staff also made weekly phone calls to check on
the status of the connection and reinforce the imminent need to complete the
work. I also met directly with the Eversource Community Relations
representative on June 3rd at DPW’s weekly construction meeting to request
that the delayed work be prioritized.
In mid-May, Eversource indicated that they would also need to receive Pole &
Conduit Commission approval for a Grant of Location for this intersection,
which was information that had not previously been communicated. Eversource
obtained approval from the Commission on May 23rd and an Eversource
representative requested that their Operations Division schedule the service
connection work for the week of June 2nd. Weather delays pushed Eversource
scheduling back to June 18th. The traffic signal was energized and put into
“flash” operation on June 19th for a one-week period in order to allow users of
the intersection to adjust to the presence of an active signal prior to full
activation. This procedure is consistent with best practices for traffic signal
activation in order to minimize potential confusion with a new traffic control
device. The signal went into full operation on Tuesday, July 2nd (following
some tree trimming to make the signal heads fully visible) and had been fully
operational since then.
As this chronology demonstrates, the City took all of the necessary actions that
are within our control in a timely manner, subject to the normal uncertainty
associated with a construction project. However, once the signal was fully built,
it took significantly longer than expected for Eversource to energize the signal,
particularly due to the delay that was associated with the second Grant of
Location, which Eversource has not previously indicated would be required.
Moving forward, when we will install traffic signals at new locations in the
future, we will begin our coordination work with Eversource even earlier than
we did for this project, to attempt to avoid a similar delay between the
completion of construction and the activation of the signal.