A communication transmitted from Louis A. DePasquale, City Manager, relative to Awaiting Report Item Numbers 19-13, 19-71 and 19-78, regarding Eversource substation expansion, energy projections and overall update on process
July 22, 2019
To:
Louis DePasquale
City Manager
From: Katherine F Watkins
City Engineer
Iram Farooq
Assistant City Manager for Community Development
Re:
Awaiting Report 19-13, dated February 4, 2019
Awaiting Report 19-71, dated June 3, 2019
Awaiting Report 19-78, dated June 10, 2019
Regarding Eversource electric Substation Expansion, Energy Projections and
Overall Update on Process
In response to the above referenced awaiting reports, please see the information below.
UPDATE ON PROCESS
The siting process for a new substation is a long process and while we do not have full
answers to all of the questions identified in the Awaiting Reports, we wanted to provide an
update on the process and share the currently available information, while we continue
the dialogue with Eversource Electric on this critical project.
ELECTRIC LOAD PROJECTIONS – WHY IS EVERSOURCE PROPOSING A NEW SUBSTATION?
According to Eversource, in August 2018, the peak electric load in East Cambridge reached
98% of all-time load. Eversource begins evaluating transmission capacity expansion once
peak loads reach approximately 75% of capacity. Operating at a high level of capacity
does not provide redundancy in the system, which is problematic in a connected electrical
grid. If a transformer overloads during heavy summer loads and there is no available
capacity as backup, portable generators would need to be brought in and / or customers
would need to be disconnected.
In addition to the existing demand, Eversource has projected future demand through 2029
and describes the need for improved power transmission capacity as follows:
“Eversource has identified an additional 20MW of new electric load in East
Cambridge through 2019 and is projecting an additional 100MW during the next
decade.“
According to Eversource, in addition to meeting additional growth, “the new
substation will enhance the reliability of the electric transmission and distribution
system in Cambridge and improve regional connectivity to enable access to renewable
energy resources. As the region continues to reduce the use of fossil fuels and increase
the amount of renewable energy, investments in the New England power grid, such as
the proposed substation, will help ensure that the renewable energy can be delivered
to serve the energy needs of Cambridge residents.”
“Access to alternative energy sources – small or large, local or remote – will be
restricted without a flexible and reliable transmission and distribution network.
Moreover, Massachusetts, and the other New England states, have ambitious goals for
carbon reduction that will require increased use of electricity to support electric
vehicles and electric building heating systems. Even when combined with
dramatically increased adoption of energy efficiency and demand response programs,
of which Eversource is a national industry leader, it is projected that demand for
electricity in communities like Cambridge will continue to increase.”
KENDALL SQUARE ENERGY ANALYSIS (2016) AND LOW CARBON ENERGY SUPPLY STRATEGY (2018)
As Eversource projects future demand for electricity, it is critical that the projections
consider a variety of factors; energy efficiency, anticipated development, and building
electrification.
In 2016, Arup analyzed energy demand in Kendall Square through 2035. The study
examined anticipated trends in energy use intensity (EUI) and energy codes and
concluded that the EUI of future buildings in Kendall would be 50% lower than those
constructed at the time of the study. In addition, it incorporated assumptions about
efficiency projects underway and anticipated future efficiency upgrades.
It found that, as a result of lower EUI in new construction, and energy efficiency projects
underway or planned, the total annual energy use is expected to remain about the same.
Peak loads, however, were projected to increase. The study also assumed that natural gas
would be the primary heating fuel, and that its use would increase.
In 2018, Ramboll built on the Arup study to project energy demand city-wide in the Low
Carbon Energy Supply Strategy study. In addition to assumptions about improved energy
efficiency in new construction and anticipated energy efficiency upgrades in the existing
building stock, the study also took into account climate change projections and the
resulting impacts on heating and cooling demand. Total annual energy demand is
projected to fall significantly as a result. However, given the importance of electrification
in enabling the use of renewable energy sources to achieve Cambridge’s Net Zero Action
Plan goals, it is vital that building electrification projections and resulting changes in
electricity demand also be incorporated into long-term planning for distribution
infrastructure.
FINANCIAL ANALYSIS AND ENVIRONMENTAL ANALYSIS OF THE SUBSTATION
At this early stage in the process, Eversource is indicating that the proposed Fulkerson
Street project is still under conceptual engineering review and cost figures and
environmental impact reports have not been finalized. If the Project advances, costs and
environmental analysis will be developed and included in the required state regulatory
filings including EPA, MEPA, DEP, and the Massachusetts Energy Facilities Siting Board
(EFSB). These reports, as well as detailed designs of the building, will be shared with
Cambridge and made publicly available once completed and available.
SITING OF NEW SUBSTATION
Eversource Electric purchased the 135 Fulkerson Street property in January 2017 after
several years of searching for potential properties. Colliers International conducted a
search of potential properties and identified fifteen potential locations. Eversource
evaluated the parcels and determined that the Fulkerson St parcel was the only viable
option considering parcel size, proximity to load and availability.
Given the concerns expressed about siting a substation at the Fulkerson St site, Eversource
and Colliers International conducted another search of properties in April and May 2019
but have been unable to find an alternative parcel that meets their requirements.
The City sponsored a meeting in early July with developers and larger property owners in
the eastern portion of the city to facilitate additional discussions regarding potential
alternative sites. Eversource has indicated that they will be continuing these discussions
directly with individual property owners. The City is also working with Eversource to
determine if any city properties could be viable alternatives. City staff have evaluated
Binney Park Parcel (intersection of Binney St and Fulkerson St) and Triangle Park Parcel
(intersection of Land Blvd and Binney St).
The Binney Park Parcel supports critical drainage, steam and telecom utilities and a
portion of the future Grand Junction Path. Once these uses are accommodated,
approximately 2/3-acre of land could be made available. Eversource is currently
evaluating whether this could be a viable site. If the Binney Park Parcel or another city
parcel is determined to be a viable site for a substation, the City would then evaluate if
using the parcel for a substation is in the City’s best interest. The Triangle Park Parcel is
about 1/3-acre and appears to be too small a site to be viable for a substation.
NEXT STEPS
City staff have a meeting in early August with Eversource staff responsible for developing
peak and base load projections to better understand the basis for the projections and
advocate for a robust, well-designed electric infrastructure in Cambridge to address not
only immediate needs but also factor in Cambridge’s plans for growth and net zero
commitments for greenhouse gas emissions reductions. Many of Cambridge’s net zero
actions and requirements will begin implementation within the 10-year planning horizon
of Eversource’s infrastructure plan. The City has asked Eversource to present non-wires
alternatives, or distributed energy and conservation measures that can help reduce the
need for additional distribution grid capacity, as demonstrated by other Eversource
projects in Massachusetts. Eversource has indicated that such alternatives must be
presented in a comparative cost-benefit analysis to state regulators as part of the
substation application process.
Another Council Hearing is also being scheduled in August to review the projections,
better understand the need for the new substation, and evaluate non-wires alternatives
including enhanced investment in energy conservation measures and battery storage to
reduce base load and demand response strategies to reduce peak load.