Search ▸ Agenda item attachment
A communication transmitted from Louis A. DePasquale, City Manager, relative to Awaiting Report Item Number 19-46, regarding whether the MBTA is in compliance with the amended Settlement Agreement in the District of Massachusetts case Daniels-Finegold et al. v. Massachusetts Bay Transportation Authority
Nancy E. Glowa ^^^^^^^^. Assistant City Solicitors
City Solicitor P^ S. Kawai
Keplm K. U. AUwaters
Arthur J. Goldberg JU S?®IK,.lil Scan M. McKendry
Dep^Ci^Sol^or Meg^B:B^
Brian A. Sch^
Samuel A. Aylesworth ''^iiii&SiSsSSS^' Katherine Sarmini Hoffman
First Assistant City Solicitor
Public Records Access Officer
Seah Levy
CITY OF CAMBRIDGE
Office of the City Solicitor
795 Massachusetts Avenue
Cambridge, Massachusetts 02139
October 7, 2019
Louis A. DePasquale
City Manager
Cambridge City Hall
795 Massachusetts Avenue
Cambridge, MA 02139
Re: Response to Awaiting Report 19-46 Re: Request to Review Whether the
Massachusetts Bay Transportation Authority Is in Compliance with the
Amended Settlement Agreement in the District of Massachusetts Case,
Daniels-Finegold et al. v. Massachusetts Bay Transportation Authority
Dear Mr. DePasquale:
We have prepared this legal opinion in response to Awaiting Report No. 19-46
(Council Order No. 0-9 of April 8, 2019), which requests that the City Solicitor's Office
review the Amended Settlement Agreement in the District of Massachusetts case Daniels-
Finegold et al. v. Massachusetts Bay Transportation Authority, C.A. No. 02CV11504 (D.
Mass. 2006), and determine whether the Massachusetts Bay Transportation Authority (the
"MBTA") is in compliance with its obligation to install an updated elevator in the Central
Square Station.
In preparing this legal opinion, my office has communicated with MBTA
representatives to obtain additional information about the status of construction at the
Central Square Station. Enclosed please find a letter dated October 27, 2019 from Laura
Brelsford, the System-Wide Accessibility Coordinator for the MBTA, and Michelle
Kalowski, Chief Legal Counsel for the MBTA, which provides an explanation for the
construction delay and estimates that construction will be completed in early 2020. In my
opinion, the MBTA has represented that they have made efforts to comply with their
* The Council Order also references dangerous stairwells in the Central Square Station. My office spoke
with MBTA representatives and they indicated that the MBTA did not have any immediate plans to fix the
stairs in the Central Square Station. In addition, the MBTA representatives denied being aware of any
complaints regarding the condition of the Central Square Station stairs and asked for clarification regarding
which stairs were an issue. There are several entrances to the Central Square Station all of which have
stairwells. In order to move forward with this matter, more information is needed regarding which stairs on
which stairwells present a safety concern to passengers.
Telephone [phone removed] Facsimile [phone removed] TTY/TTD (61 7) 349-4242
obligations under the Amended Settlement Agreement to install an updated elevator in the
Central Square Station.
Amended Settlement Agreement
On July 25, 2002, the plaintiffs brought a civil action in the United States District
Court of Massachusetts for declaratory and injunctive relief against the MBTA, Daniels-
Finegold et aL v. MBTA. C.A. No. 02CV11504. Specifically, the plaintiffs alleged that
MBTA services were not readily accessible to and usable by individuals with mobility,
hearing, and visual disabilities In violation of the Americans with Disabilities Act.
On June 15, 2006, the Court accepted the parties' Settlement Agreement. In the
Settlement Agreement, the MBTA agreed to establish, operate, and maintain its services in
a manner which made them readily accessible and usable to all persons, including
individuals with disabilities. The case remained open with the Court retaining jurisdiction
to ensure that the MBTA performed its obligations under the Settlement Agreement.
On December 4, 2018, the parties executed an Amended Settlement Agreement to
reflect the progress that had been made since entering into the original Settlement
Agreement. The Amended Settlement Agreement identified three (3) categories of
obligations: substantially satisfied obligations, obligations requiring additional action, and
obligations requiring modification.
Under the Amended Settlement Agreement, one of the MBTA s ongoing obligations
related to elevator usage. Specifically, the MBTA agreed to maintain and operate elevators
in a manner which made them readily accessible and usable by persons with disabilities
during all passenger service hours. To accomplish this goal, the MBTA agreed to "design,
fund, and implement an elevator management plan to provide continuous, uninterrupted
elevator service during all passenger service hours, subject only to temporary and isolated
elevator outages for repairs, maintenance, and inspections." Amended Settlement Agreement
at §53. Pursuant to the Amended Settlement Agreement, the MBTA would be considered
out of compliance with its obligation to maintain continuous elevator service "if, during any
one-month period, the number or duration of outages for any elevator in the MBTA
passenger service system is more than insubstantial. Id. at §54.
In addition, the MBTA agreed to replace certain elevators, including elevator #861
in the Central Square Station. Id. at §56. The Amended Settlement Agreement did not
provide a specific date or timeframe for completion of this elevator replacement.
During elevator outages, the MBTA is required to establish a dedicated means of
alternative transportation and to promptly publicize this information to passengers. Id. at
§§§62, 66,and 74. In addition, the MBTA is required to provide alternative transportation
services in a "timely manner." M at §72. Specifically, with respect to the Central Square
Station elevator replacement, the MBTA has established and publicized two (2) alternative
transportation options: (1) a bus shuttle which transports passengers from Massachusetts
Avenue to Kendall Square and (2) an outbound service elevator at the Harvard Square
Station.
II. Status of Construction at the Central Square Station
As detailed above, in accordance with the Amended Settlement Agreement, the
MBTA is required to replace the elevator in the Central Square Station with a larger, more
modem elevator. Based on earlier estimates, the MBTA anticipated that construction
would be completed by spring 2019.
According to MBTA representatives, construction has been delayed by several
unforeseen issues. Specifically, during construction, workers observed a nearby stand
pipe. A state building inspector conducted an inspection of the stand pipe, which included
administration ofapre-air test. The stand pipe failed the pre-air test, and the state building
inspector determined that the stand pipe was a safety hazard. The state building inspector
refused to allow construction on the elevator to proceed until the stand pipe issue was
remedied. Repair of the stand pipe required the expenditure of significant time and
resources. In addition to the stand pipe, the MBTA discovered seventeen (17) existing
conduits in the elevator shaft that needed to be relocated in order to continue with
construction. Furthermore, the MBTA is only allowed to engage in construction and repair
activities during off hours between 1:30am to 5:00am so as not to disrupt daily service.
These limited work hours further contributed to the construction delays.
The MBTA has remedied the unforeseen issues encountered during construction
and is moving forward with replacement of the elevator. Based on these unforeseen issues,
construction has been delayed approximately ten (10) months. The MBTA anticipates that
construction will be completed by early 2020.
III. Analysis
The MBTA has represented to the City that they have made efforts to comply with
their obligations under the Amended Settlement Agreement to install an updated elevator
in the Central Square Station. Specifically, the MBTA has reported that they are in the
midst of replacing the elevator in question. Unfortunately, because of previously
unforeseen issues, construction was delayed for approximately ten (10) months. The
MBTA remedied the stand pipe and conduit issues that were discovered during
construction. Furthermore, the Amended Settlement Agreement does not specify a date or
timeframe for completion of the elevator replacement; accordingly, the MBTA does not
appear to be in direct violation of its replacement obligation because of the construction
delays.
While the Amended Settlement Agreement includes a provision regarding the
MBTA's general requirement to maintain continuous elevator service and the standard for
determining noncompliance with this requirement, this provision does not appear to apply
to the Central Square Station elevator replacement. The Central Square Station elevator
replacement is addressed in a different section of the Amended Settlement Agreement and,
as detailed above, does not include a date or timeframe for required completion. Requiring
the MBTA to provide continuous elevator service during a long-term, complicated
construction project does not seem possible.
Finally, the MBTA has reported that it is in compliance with its obligation to
establish and publicize alternative transportation routes during the Central Square Station
elevator outage. Specifically, the MBTA has established and publicized two (2) alternative
options, including a bus service option and an elevator service option at the nearby
Harvard Square Station. The MBTA is required to provide alternative transportation in a
timely manner and could be in violation of §72 of the Amended Settlement Agreement if
alternative transportation is not being provided in a timely manner. To the extent that there
are allegations that alternative transportation is not being provided in timely manner, it is
not clear whether the alternative transportation delays are the same delays attributable to
weather and mechanical issues, which effect all MBTA services and passengers.
In conclusion, the MBTA has represented that it has made efforts to fulfill its
Amended Settlement Agreement obligation to replace the elevator at the Central Square
Station notwithstanding unforeseen issues. In addition, the MBTA has reported that it has
established and publicized alternate transportation routes while construction is ongoing in
accordance with its Amended Settlement Agreement requirements.
Very truly yours,
Nanc^E.^Glowa
City SoTicitor
Enclosure
Chcirk's D, B^hci. Governor
Karyn E. Potito. Ueutenant Governor
Stephanie Pollack, MassDOT Secrctjry h CEO
Steve Poftak, General Mcinager Massachusetts Department of Transportation
massDOT
September 27, 2019
Cambridge City Council
Cambridge City Hall
795 Massachusetts Ave.
Cambridge, MA 02139
Re: Construction of Replacement Elevator at Central Square Station
Dear Council Members,
The Massachusetts Bay Transportation Authority (MBTA) understands that the City
Solicitor is providing you with information regarding the delay to the construction of the
replacement elevator at MBTA's Central Square (Inbound) station. The MBTA appreciates
the Council's attention and concern regarding this issue.
MBTA recognizes that the elevator outage at Central Square has had a serious impact on
customers' commutes, and MBTA shares your desire that the elevator is returned to
service as quickly as possible. As you may know, MBTA began construction to the
elevator unit construction so that it could be replaced with a larger, safer and more
modernized unit. Shortly after construction began, unfortunately, a number of unexpected
complications arose (including standpipe repairs and conduit that needed relocating) that
could only be addressed during non-revenue hours (three hours per day). These
complications delayed the replacement of the elevator.
The outstanding construction issues have now been resolved, and MBTA anticipates that
the new unit will open for service in early 2020. The project team continues to look for
opportunities to accelerate the schedule and will keep you updated if there are any
changes. In the meantime, a shuttle bus will continue to connect customers between
MBTA's Central and Kendail stations.
The MBTA remains committed to being accessible for all of its customers and is striving to
become a model of accessible public transportation. Please do not hesitate to contact us if
we can provide further information or answer questions.
Sincerely,
1^ \,,1
^^-^\^ l^l';J ^/L
Laura Brelsford Michelle Kalowski
AGM, System-Wide Accessibility Chief Counsel
Massachusetts Bay Transportation Authority
Ten Park Plaza, Boston, MA 02116
www.mbta.com