Search ▸ Agenda item attachment
Transmitting Communication from Louis A. DePasquale, City Manager, relative to the appropriation and authorization to borrow $14,600,000 to provide funds for the Municipal Facilities Improvement Plan. PASSED TO SECOND READING IN COUNCIL MAY 2, 2022 TO BE ADOPTED ON OR AFTER MAY 23, 2022
City of Cambridge
CAL-02
Agenda Item Number 6
IN CITY COUNCIL
May 2, 2022
June 6, 2022
ORDERED:
That $14,600,000 is appropriated, in addition to any amounts previously
appropriated, for the purpose of planning and financing building renovations,
including all costs incidental or related thereto, including but not limited to the
following projects in the municipal facilities improvement plan: upgrades to the
City Hall Annex geothermal well system and building envelope improvements;
HVAC improvements at the Moses Youth Center; City Hall façade repairs;
electric vehicle charging station infrastructure at several municipal buildings;
HVAC upgrades at the Healy Public Safety building and O'Connell Branch
Library; and additional work at Taylor Square and East Cambridge Fire Houses
and other fire stations; and to meet this appropriation the Treasurer with the
approval of the City Manager is authorized to borrow $14,600,000 under
Chapter 44 of the General Laws or any other enabling authority.
In City Council June 6, 2022.
Adopted by a yea and nay vote:-
Yeas 9; Nays 0; Absent 0.
Attest:- Paula M. Crane, Interim City Clerk
A true copy;
ATTEST:-
Paula M. Crane,
Interim City Clerk