Search ▸ Agenda item attachment
CMA 2017 #309 · Agenda item attachment · Dec 4 2017
A communication transmitted from Louis A. DePasquale, City Manager, relative to Awaiting Report Item Numbers 17-81, regarding speeding on Field Street and Awaiting Report Item Number 17-106, regarding West Cambridge (Alewife) Sewer Separation
City of Cambridge
Department of Public Works
Owen O'Riordan, Commissioner
147 Hampshire Street
Cambridge, MA 02139
theworks@cambridgema.gov
Voice: [phone removed]
TDD: [phone removed]
November 28, 2017
To:
Louis DePasquale
City Manager
From: Katherine F. Watkins, City Engineer
Joe Barr, Director, Traffic, Parking & Transportation
Re:
Awaiting Report 17-106, dated October 2, 2017
Regarding West Cambridge (Alewife) Sewer Separation
Awaiting Report 17-81, dated September 11, 2017
Regarding Speeding on Field Street
In response to the council orders regarding the Alewife Sewer Separation project, staff report
the following:
ALEWIFE SEWER SEPARATION PROJECT AND FEDERAL COURT ORDER:
The Alewife Sewer Separation project was part of the court-ordered Massachusetts Water
Resources Authority’s (MWRA) Long-Term Control Plan for reducing combined Sewer
Overflows (CSOs) and improving the water quality of the Boston Harbor. The City met the
federal court milestone for sewer separation in December 2015, marking a significant
achievement for the City, the MWRA and the region. Combined Sewer Overflows from the
Alewife neighborhood have been eliminated, directly improving water quality of the Alewife
Brook, Mystic River and Boston Harbor.
An excerpt from the Final MWRA Annual Report to the Federal Court provides some context
for the project and highlights its importance.
In the late 1980s, the Boston area had the dubious distinction of having the dirtiest
harbor in America. If someone fell into the Charles, Mystic, and Neponset Rivers, a trip
to the hospital for disinfection was strongly recommended. The urban beaches were
frequently closed for days, even after the most modest of rain events.... Residents living
along the waterfront often had to close their windows because of the foul smell of the
harbor. The situation was a national embarrassment for the region.
Today, the results of our efforts are an irrefutable success. Our beaches are now
considered the cleanest urban beaches in the country. The water quality of the Charles
and Mystic Rivers has been rated a B plus. In fact, swimming races are held in the
Charles River and efforts are afoot to reopen a bathing beach. The greater harbor has
rejuvenated itself and is swimmable, even during rain events. It is truly a great
environmental success story and the CSO program has played a critical role.
Our partners at the Boston Water and Sewer Commission, Cambridge, Brookline, and
Chelsea deserve high praise for their professionalism in completing the difficult projects
in their communities. Further I thank the residents and businesses for their patience
through the disruptive construction on their streets and in their neighborhoods.
Fred Laskey, Executive Director, MWRA
OTHER IMPROVEMENTS:
Although the primary goals of the project were to complete sewer separation; protect local
waterways and improve water quality, the project provided an opportunity to improve
infrastructure throughout the contract areas. The contracts included:
• 15 miles of sidewalks
• 150 pedestrian ramps
• 10.5 miles of new sewer and drain mains
• 6 miles of gas mains
• 6 miles of water mains
• 300 new street trees
While the community was significantly impacted and inconvenienced by the construction, the
benefits of the improved utilities, streets and sidewalks will benefit the community and the
larger region for generations.
STREET DESIGNS:
The design of the streets in the three contract areas was established through an extensive
community process where city staff presented Traffic Calming and Complete Streets’ principles
as a basis for designing streets that are accessible and friendly to all users. The designs include
fully accessible sidewalks; curb extensions at crosswalks, existing trees and new trees; raised
crosswalks; new crosswalk locations; rain gardens and other design elements that have
improved safety and enhanced the street experience for all users.
The overall approach to a comprehensive street design and the impact of construction on the
community was recognized by Judge Stearns, the Federal Judge overseeing the Boston Harbor
Cleanup:
I am very impressed with the surface restoration work that is now underway in
Cambridge, especially the innovative and attractive “green” storm water runoff basins
that are being installed. The restoration work … will be enduring gifts to the City and
citizens of Cambridge who have endured the disruptions and inconveniences that this
massive (and necessary) undertaking has entailed.
Judge Stearns
United States District Court of Massachusetts
Compliance Order Number 238
December 21, 2015
SPEEDING CONCERNS:
The City will be evaluating speeds on the various streets and is currently collecting traffic
volumes and speeds in an effort to review the post construction conditions. With the extensive
number of streets, the data collection will take at least a month to collect and then some time to
process. City staff can then evaluate concerns about speeding and determine if additional
modifications are warranted.
SCHEDULE AND COST CHANGES:
Given the size of the Alewife Sewer Separation area, the project was broken in to 3 contracts:
Huron A, Huron B and Concord Ave. The duration of each of the contracts was extended by
approximately one year from its original schedule.
Huron A
Contract Start:
September 2012
Original Completion: December 2014
Actual Completion: November 2015
Huron B
Contract Start:
September 2013
Original Completion: September 2016
Actual Completion:
December 2017
Concord Ave
Contract Start:
February 2014
Original Completion: August 2016
Actual Completion:
August 2017
The overall value of the contracts has increased from the original bid value of $69,700,000 to
$90,300,000. The most significant increase in cost was associated with the replacement of the
over 100-year-old riveted steel 40” water transmission main on Huron Avenue between Fresh
Pond Parkway and Gurney Street ($7,500,000).
These schedule delays and cost increases are consistent with what we would expect for this type
of heavy utility construction, in a dense urban environment and are primarily associated with
added work items such as the replacement of the over 100-year-old 40” water transmission main
on Huron Avenue; extensive coordination required between the three contracts; coordination
with private utility companies such as Eversouce Gas, which has replaced over 6 miles of gas
mains in the contract areas; planting of trees that are season dependent; resequencing of work to
ensure the completion of the sewer separation by December 2015; and schedule modifications
to reduce impacts on residents and businesses, such as prohibiting significant construction on
Huron Avenue in the business district between Thanksgiving and New Year’s in both 2015 and
2016.
Contract
Bid Value
Huron Ave Water
Main
Change
Orders
Total Value to
Complete
Huron A
$15,500,000
$3,900,000
$19,400,000
Huron B
$30,000,000 $7,500,000
$5,400,000
$42,900,000
Concord
Ave
$24,200,000
$3,800,000
$28,000,000
Totals
$69,700,000 $7,500,000
$13,100,000
$90,300,000
Approximately 50% of the project costs are funded by the MWRA and 50% by the City.
FUTURE UTILITY PROJECTS:
For all of the City’s major construction projects, staff work closely with residents and
businesses to prepare them for the construction and try to minimize the disruption. However,
we know that construction is always challenging and disruptive – particularly large-scale utility
77%
8%
15%
HURON A, HURON B & CONCORD AVE
Bid Value: $69.7M
Water Main: $7.5M
Change Orders: $13.1M
construction like the Alewife Sewer Separation Project, the recently completed Western Avenue
project, or the upcoming Port Project.
Staff are frequently asked how the next city project will be different from the Alewife Sewer
Separation Project. The Alewife project involved $100M of construction in a dense residential
neighborhood subject to a challenging court-ordered schedule. Other city projects are typically
smaller in scale and not subject to a court-ordered schedule, so they can be phased. The first
phase of the Western Avenue Program (Western Avenue and the new stormwater outfall) was
approximately $20M and the first phase of the Port Project (Parking Lot 6 tank) is estimated at
$20M. The first phase of the Port Project is scheduled to begin in spring 2018 and will have
limited impact on residential streets; being contained mostly in the City’s Parking Lot 6, with
utility connections on Bishop Allen Drive and Mass. Ave. The second phase of the Port Project
will involve the neighborhood streets and we will work with the community to evaluate phasing
alternatives. The design process for the second phase will begin in 2018, with construction to
begin in 2019, pending input from the community on how best to phase the work.