Search ▸ Agenda item attachment
That the City Manager confer with Eversource and the appropriate City departments to undertake a series of studies and analyses related to finance, health and safety, building design, and long-term electricity needs before the construction of a substation in East Cambridge
City of Cambridge
O-3
ORIGINAL ORDER
IN CITY COUNCIL
February 4, 2019
COUNCILLOR MALLON
MAYOR MCGOVERN
COUNCILLOR TOOMEY
COUNCILLOR SIDDIQUI
WHEREAS:
In 2018, Eversource purchased a plot of land in East Cambridge adjacent to
Alexandria Real Estate’s proposed Metropolitan Pipe site, as well as the Linden
Park neighborhood, and the Kennedy Longfellow Elementary School; and
WHEREAS:
The City of Cambridge has a goal to encourage distributed district energy generation
and transition away from fossil fuel-based energy to renewable energy sources; and
WHEREAS:
Public utility companies are not subject to municipal zoning regulations; however, it is
still vital to ensure that the proper health and environmental impact studies have been
conducted by the public utility company; now therefore be it
ORDERED:
That the City Manager be and hereby is requested to confer with Eversource
and the appropriate City departments to ensure that Eversource has undertaken
the following analyses and impact reports before moving forward with the
construction of their substation:
•
A financial disclosure and analysis of how the cost of the site in East
Cambridge and construction of the substation will potentially impact
costs for ratepayers, who have already faced increases this winter,
particularly since the site alone, without construction factored in, cost
Eversource $13 million
•
A study demonstrating why this substation is required and how it affects
the City’s goals of moving towards alternative energy sources, such as
renewables
•
An environmental impact study of the health and safety impacts of
locating a large substation adjacent to a residential neighborhood and
elementary school
•
Renderings that show building and site design, and indicate the
substation’s footprint, height, and other critical design features;
•
Long term electricity demand projections for the City of Cambridge
including, if available, the predicted need to expand or add other
substations in Cambridge in addition to the planned substation at
Fulkerson Street to satisfy anticipated future need for electricity; and be it
further
ORDERED:
That the City Manager be and hereby is requested to make the results of these
analyses and impact reports widely available to the public with an emphasis on
the direct abutters of the site; and be it further
ORDERED:
That the City Manager be and hereby is requested to work with the Community
Development Department and the Department of Public Works to report on
how the construction of this substation will impact the City’s move towards
renewable energy; and be it further
ORDERED:
That the City Manager be and hereby is requested to report back to the City
Council on this matter as soon as possible.