An application was received from Jeff Perenti, requesting permission for a curb cut at the premises numbered 11 Education Street; said petition has received approval from Inspectional Services, Traffic, Parking and Transportation, Historical Commission and Public Works. No response has been received from the neighborhood association
General Information
Attestation
Attachments (6)
Curb Cut
77480
Status: Active
Submitted: Jun 19, 2020
Applicant
Jeff Parenti
[phone removed]
jeffrey.parenti@mass.gov
Location
11 Education St
Cambridge, MA 02141
Frontage (in feet)
30
Setback - distance from building to sidewalk (in feet)
360
Distance from proposed driveway to surrounding structures
and property line (in feet)
4
Length of proposed driveway (in feet)
230
Width of proposed driveway (in feet)
25
Size of proposed driveway (square feet)
5750
Location of any trees, sign posts, fire hydrants, utility poles, etc., in direct vicinity of proposed driveway
Street light pole; 9" little leaf linden
Full Name
Jeffrey R. Parenti
Date
06/19/2020
Photographs of the property
Jun 18, 2020
pdf
pdf
Certified Plot Plan (survey)
Jun 18, 2020
Abutters Forms
Jun 18, 2020
Page 1 of 2
7/23/2020
https://cambridgema.viewpointcloud.io/
Timeline
pdf
pdf
pdf
Plan of Requested Conditions
Jun 18, 2020
unsigned neighborhood association letter_6.23.2020.pdf
Jun 23, 2020
11 Education Street curb cub permit application -- cover letter.pdf
Jun 23, 2020
Original Submission
Status: Issued June 19th 2020, 8:31 am
Review for Completeness
Status: Completed June 19th 2020, 9:36 am
Assignee: Sean O'Grady
Zoning Review
Status: Completed June 19th 2020, 9:37 am
Assignee: Sean O'Grady
City Clerk Review
Status: Completed June 23rd 2020, 12:20 pm
Assignee: Lori Perez
Lori Perez June 23rd 2020, 12:20:02 pm
Unsigned Neighborhood Association letter uploaded and emailed to East Cambridge - Neighborhood 1
(https://www.cambridgema.gov/CDD/planud/neighplan/neighs/1) . 6.23.2020
Traffic & Parking Department Review
Status: Completed June 23rd 2020, 1:25 pm
Assignee: Stephen Meuse
Stephen Meuse June 23rd 2020, 1:25:01 pm
per P. Baxter.
Department of Public Works Review
Status: Completed June 23rd 2020, 2:30 pm
Assignee: TJ Shea
TJ Shea June 23rd 2020, 2:30:04 pm
DPW approved. Contractor must apply for excavation permit prior to commencing work. Driveway transition to be concrete per
Cambridge standard details
City Clerk Review for City Council Agenda
Status: In Progress
Assignee: Lori Perez
City Council Approval
Status: Pending
Department of Public Works - Next Steps
Status: Pending
Page 2 of 2
7/23/2020
https://cambridgema.viewpointcloud.io/
June 18, 2020
To Whom It May Concern:
I am writing to express DivcoWest’s support for the Department of Conservation and Recreation’s (DCR)
request for a curb cut on Education Circle.
DivcoWest is an abutter to the land owned by the Commonwealth on which DCR is constructing their
maintenance facility, which would be served by this new curb cut. We support the construction of the
maintenance facility and the modifications DCR has made to save existing trees on Education Circle.
Sincerely,
DIVCOWEST REAL ESTATE INVESTMENTS
Mark Johnson
Mark Johnson
Director of Development
Project # 18-136
DCR North Point Maintenance Facility
11 Education Street Cambridge, Ma
DCR Maintenance Facility Abutters Form
As part of the new DCR NorthPoint Maintenance Facility a new driveway is to be installed to
provide access from NorthPoint Blvd as shown in the plans below. As part of the Cambridge
Curb Cut permit application abutters of the property must be informed of the new curb cut
location.
Signing your name below indicates United Civil has informed you of the proposed work that will
be taking place near/ along/ abutting your property.
If there aren’t any issues or concerns, a signature below would be deeply appreciated.
Signature:
Address:
Date:
EF Education First, 2 Education Circle, Cambridge
6/18/20
COMMONWEALTH OF MASSACHUSETTS · EXECUTIVE OFFICE OF ENERGY & ENVIRONMENTAL AFFAIRS
Department of Conservation and Recreation
251 Causeway Street, Suite 600
Boston, MA 02114
[phone removed] [phone removed] Fax
www.mass.gov/orgs/department-of-conservation-recreation
Charles D. Baker
Governor
Karyn E. Polito
Lt. Governor
Kathleen A. Theoharides, Secretary
Executive Office of Energy & Environmental Affairs
Jim Montgomery, Commissioner
Department of Conservation & Recreation
Cambridge City Council
City Hall
795 Massachusetts Avenue
Cambridge, MA 02139
RE: DCR Curb Cut Permit Application, 11 Education Street
Members of the City Council,
The purpose of this letter is to provide some additional information and context for this request
to augment our curb cut permit application.
The Department of Conservation and Recreation (DCR) is nearing completion of its new
maintenance facility in North Point. The DCR North Point Maintenance Facility is a 35,000
square foot building, service yard, and fueling station on a four-acre parcel in the North Point
area of Cambridge. This facility will serve as the primary operations center for DCR in the
Greater Cambridge and Boston Region. Among the many responsibilities of DCR is the safety,
maintenance, and repairs of parklands and parkways, such as Memorial Drive, Alewife Brook
Parkway, Land Boulevard, and Fresh Pond Parkway. Our largest special events, such as the July
4 Boston Pops concert and fireworks display, will be based from the North Point facility.
Cambridge DPW and TP+TD staff have generously given their time to assist us with this
request, which presents a unique design challenge. At the end of the facility’s service driveway,
there is a 9” mature little leaf linden. Our preferred driveway proposal was to extend the
driveway directly to North Point Boulevard, remove the tree, and construct a traditional curb cut
perpendicular to the curb line.
City staff expressed a strong desire to retain the tree. DCR staff met with Cambridge several
times – once at 147 Hampshire Street and twice on site – to brainstorm how to build the
driveway around the tree.
To the right of the tree, part of the relocated driveway would need to pass through the MWRA
Prison Point property. On the left, a street light pole and a catch basin would need to be
relocated. On either side, the driveway would need to be angled to keep it clear of the tree.
As a result of this collaboration between DCR and the City, we agreed to alter the driveway
alignment to save the tree. Although an angled driveway layout is unusual, we concluded that it
would adequately serve the needs of the maintenance facility and the Operations vehicles that
will use it.
Again, we are very grateful that Cambridge staff have worked with us on this request. We
appreciate the collaboration that we feel it has resulted in a solution that allows us to open and
operate from our new facility while saving the little leaf linden.
Here are a few additional notes on this request:
• The North Point Maintenance Facility does have an additional egress onto Education
Street, but that entrance is intended for visitors and passenger cars. The North Point
Boulevard access is much closer to the operations vehicle storage and service and
materials storage and is designed to accommodate larger vehicles.
• The driveway is on state land and not subject to Cambridge zoning regulations
• Except for EF Education First, the maintenance facility abutters are also state agencies
(MBTA and MWRA).
Sincerely,
Jeffrey R. Parenti, PE, PTOE, PTP, ENV SP
Deputy Chief Engineer
cc:
Patrice Kish, Chief, DCR Division of Design and Engineering
Robin Pfetsch, Director, Architecture Section, DCR Design and Engineering
Katherine F. Watkins, City Engineer
M
NORTH POINT BOULEVARD
SCALE IN FEET
0
10
10
20
Project Name:
DCAMM Project Number
Project Location
Project Architect
Project Consultant
Site Number: MDCF9
CAMIS Number: 5MDC0401
Building Number:
Secretariat: EOEEA
Original Issued Date
Revisions
No.
Description
Date
Sheet Name:
Drawing Number:
Drawing
of
Douglas Dick AIA
LDa Architecture & Interiors, LLP
222 Third Street, Suite 3212
Cambridge, MA 02142
[phone removed]
www.LDa-Architects.com
VHB
101 Walnut Street
Watertown, MA 0247[phone removed]
www.vhb.com
07/06/2018 - CONSTRUCTION
DCR 1110-DC1
11 EDUCATION STREET
CAMBRIDGE, MA 02141
DCR North Point Maintenance Facility
ACCESS ROAD ENTRANCE
CURB CUT PERMIT
1
1
N
5.0'