Transmitting Communication from Yi-An Huang, City Manager, relative to the appropriation of $100,000 received from the Massachusetts School Building Authority (MSBA) to the Public Investment Fund School Extraordinary Expenditures account to fund a feasibility study and schematic design costs for the roof replacement project at the Cambridgeport School, located at 89 Elm Street.
⚠ This document is a scan; its text was recovered by optical character recognition and may contain errors. The original PDF is authoritative.
26-007
CAMBRIDGE PUBLIC SCHOOLS
135 Berkshire Street, Cambridge, Massachusetts 02141
January 20, 2026
TO THE HONORABLE MEMBERS OF THE SCHOOL COMMITTEE:
Approval of Authorization for the Superintendent to submit an Initial Compliance Certification to enter
into a Feasibility Study/Schematic Design agreement with the Massachusetts School
Building Authority for the replacement of the Cambridgeport School building roof, and to appropriate
funds for this agreement.
Recommendation:
Approval of Authorization for the Superintendent to submit an Initial
Compliance Certification to enter into a Feasibility Study/Schematic Design
agreement with the Massachusetts School Building Authority for the replacement
of the Cambridgeport School building roof, and to appropriate funds for this
agreement. That in accordance with the requirements of the Massachusetts
School Building Authority the School Committee enter an order containing the
following:
That the City of Cambridge hereby appropriates the amount of one hundred
thousand ($100,000) Dollars for the purpose of paying feasibility study and
schematic design costs related to a potential Accelerated Repair Project involving
the roof replacement at the Cambridgeport School located at 89 Elm Street in
Cambridge, MA, including the payment of all costs incidental or related thereto
(the "Project"), which proposed repair project would materially extend the useful
life of the school and preserve an asset that otherwise is capable of supporting the
required educational program, and for which the City of Cambridge has applied
for a grant from the Massachusetts School Building Authority (the "MSBA"),
said amount to be expended under the direction of the School Committee of
Cambridge Public Schools. To meet this appropriation, the City Council, with the
approval of the City Manager, is authorized to appropriate from available funds
said amount under M.G.L Chapter 44, or any other enabling authority. The City
of Cambridge acknowledges that the MSBA's grant program is a non-
entitlement, discretionary program based on need, as determined by the MISBA,
and if the MSBA's Board of Directors votes to invite the City to collaborate with
the MSBA on this proposed repair project, any project costs the City of
Cambridge incurs in excess of any grant that may be approved by and received
from the MSBA shall be the sole responsibility of the City of Cambridge.
The language set forth above is the form of vote required by the Massachusetts
Description:
School Building Authority in order for the appropriation for Feasibility
Study/Schematic Design to be submitted to the Massachusetts School Building
Authority.
Respectfully submitted,
David Murphy,
Superintendent of Schools