CMA 2022-130
The second Progress Report due under the Cycling Safety Ordinance (Chapter 12.22 of the Cambridge Municipal Code), which is required to detail “…progress towards meeting the requirements set forth in Subsections C, D, E, F, G, and H
Voted yes (9), unanimous
Dennis Carlone
Patty Nolan
Paul F. Toner
Alanna Mallon
Marc McGovern
Sumbul Siddiqui
E. Denise Simmons
Burhan Azeem
Quinton Zondervan
Introduction Cambridge’s Cycling Safety Ordinance requires annual progress reports on improvements made each year. Many deadlines and timelines set out in the Ordinance follow a “Separated Bike Lane Year” from May 1 through April 30. This second annual report: Details improvements made in Separated Bike Lane Year 2 (from May 1, 2021, to April 30, 2022). Outlines the work planned for Separated Bike Lane Year 3 (from May 1, 2022, to April 30, 2023). Counts mileage totals as indicated in the Cycling Safety Ordinance. Quick-build projects are counted in the year when they are installed, and capital construction lanes are counted in the year that construction starts.
Separated Bike Lane Construction Summary
In Year 1, we completed 4.12 miles of separated bike lanes. In Year 2, we completed 2.11 miles of separated bike lanes and designed another .56 miles. In Year 3, we plan to install the .56 miles of separated bike lanes designed in Year 2, and to install or start construction on an additional 3.67 miles, for a total of 4.23 miles. In Year 3, we also plan to start public engagement on the Hampshire Street corridor and to set up a stakeholder working group for the Cambridge Street corridor. We do not anticipate installation of either the Hampshire Street or Cambridge Street project during Year 3.
3
Cycling Safety Ordinance Background
In 2019, the Cambridge City Council passed the Cycling Safety Ordinance. The Ordinance requires the construction of separated bike lanes when streets that have been designated for greater separation in the Bicycle Network Vision are being reconstructed as a part of the City’s Five-Year Plan for Streets and Sidewalks.
In 2020, the Council passed amendments to the Cycling Safety Ordinance, setting ambitious requirements for the installation of approximately 25 miles of separated bike lanes within the next five to seven years. The location of these facilities will be informed by both the Cambridge Bicycle Network Vision and specific requirements in the Ordinance. In general, the amendments to the Ordinance require the installation of separated bike lanes on: all of Massachusetts
Broadway from Quincy
Street to Hampshire Street
Cambridge Street from
Oak Street to Second
Hampshire Street from
Amory Street to Broadway
Garden Street, eastbound
from Huron Avenue to Berkeley Street, and westbound from Mason
Street to Huron Avenue
Streets that the Cycling Safety Ordinance requires the installation of separated bike lanes on.
The Ordinance also requires 11.6
more miles of separated bike lanes in other locations that are part of the Bicycle Network Vision. The Ordinance distinguishes between quick-build and construction. Quick-build methods include pavement markings, flex-posts, signage, and signal changes. Construction involves more extensive changes, including potentially moving curbs and/or removing medians.
Work becomes more complex any time we dig into the ground, and construction projects may include work on the infrastructure (e.g., water, drainage and sewer pipes, traffic signals) that we have underground. For additional information about the Cycling Safety Ordinance, please visit www.cambridgema.gov/cyclingsafetyordinance. This page details the specific requirements and the associated timelines and provides additional links to individual Cycling Safety Ordinance projects.
4
Work Completed During Separated Bike Lane Year 2:
May 1, 2021 through April 30, 2022
Completed Quick-Build Projects and Initiated Capital Construction Projects
Dudley St to
Alewife Brook
Parkway 0.90 Cambridge St to
Waterhouse St
northbound 0.06 Plympton St to
Bow St
northbound 0.06 Trowbridge St to
Pleasant St
0.92
Somerville Avenue White St
Line to City 0.12
Church St to St JFK southbound 0.05
Capital project: Construction
has begun on the Harvard Square Kiosk and Plaza Project.
Total for Year 2
2.11 miles Mid-Mass Ave. Safety Improvement Project 5 Several projects were designed during Year 2 but were not installed by the April 30 deadline. We expect to install these projects in 2022. See “Work Planned in Separated Bike Lane Year 3” for a list of these projects.
MassAve4 Progress
In the Cycling Safety
Ordinance, sections of
Massachusetts Avenue
that have complicating factors were identified and are now referred to as the “MassAve4” (see adjacent map). These complications are two major bus stops in
Harvard Square
and two sections of the street with overhead bus wires. The City completed an impacts analysis (as required in the Cycling Safety Ordinance) and submitted the analysis to the City Council on April 30, 2021. Since the submission of this analysis, the City has conducted further analysis and public engagement around the MassAve4. In April 2022, the City submitted a report to the City Council with recommended approaches and timelines for the installation of separated bike lanes on these four segments.
The full report can be found here. The recommended projects are now included in the City's 5 Year Capital Plan, including $40 million for Harvard to Alewife Brook Parkway and $15 million for the Harvard Square bus stops. In summary, the report recommends implementing bike lanes through: Partial construction for the segments of Massachusetts Avenue with overhead MBTA bus wires and median – the segment from Dudley Street to Beech Street and the segment from Roseland Street to Waterhouse Street.
“Partial construction” would remove the center median except at key pedestrian crossing locations and install flex posts or curbed bike lane separation. Full construction for the Harvard Square bus stops – the segment of Massachusetts Avenue from Church Street to Garden Street and the segment from Plympton Street to Dunster Street. “Full construction” would allow for bike lanes to be raised to sidewalk level and for bus stop islands to be placed next to the curb.
MassAve4 Segments
6
Work Planned for Separated Bike Lane Year 3:
May 1, 2022 through April 30, 2023
It is important to note that the workplan laid out here for the upcoming year reflects the best of our knowledge at the time of this report and is subject to change. There are various factors that can impact implementation schedules, including the need for extended community engagement and coordination with utility work or other construction.
Designed During Year 2
The following projects were designed during Year 2 but were not installed by the April 30 deadline. We expect to install these projects before the end of the 2022 construction season. The mileage will be recorded in Year 3. Roseland St to
Beech St
Both 0.41 Community engagement has begun. Anticipated completion summer 2022. Memorial Drive to 77 Mass Ave northbound .12 Plans and outreach complete.
Anticipated completion by June
2022. 33 Mass Ave to
Memorial Dr
northbound .03 Plans and outreach complete.
Anticipated completion by June
2022. Total .56 miles
Dudley Street to Alewife Brook Parkway Separated Bike Lanes
7
Planned for Year 3
The following projects are planned for Year 3.
Cambridge Street
Oak St to
Prospect St