CMA 2026-137
An update on the successful completion of the 221 Mount Auburn Street demolition
Present and voting at this meeting (9)
Ayah Al-Zubi
Burhan Azeem
Tim Flaherty
Marc McGovern
Patty Nolan
Sumbul Siddiqui
E. Denise Simmons
Jivan Sobrinho-Wheeler
Cathie Zusy
City April 28, 2025
7 Punching Shear -- The slab needs to be strong enough to support the weight 8 Slab Column 9 Asbestos Consistent with buildings of this era, chrysotile asbestos was identified in joint compound, floor tiles and popcorn ceilings. Asbestos is a naturally occurring mineral found in the ground. Widely used in buildings due to its fire and heat resistance, durability and insulation until health risks associated with airborne asbestos became apparent. Individual asbestos fibers are too small to see with the human eye. www.mesotheliomahub.com/mesothelioma/asbestos/types-of-asbestos/
City Involvement
10 11
Timeline for City Involvement
• April 2025 – City began regular meetings with owners • Consensus – building must be demolished • City’s involvement is based on public health & safety • July – met individually with all neighbors • In-person meeting July 10th – 80 people • July 19th – Closed Mt. Auburn & Sparks streets • July 22nd – Board or Survey • City Council appropriated $20M on July 23rd. • Zoom meeting July 24th – over 200 people • Zoom meeting October 22, 2025 – meet the team 12
Timeline for City Involvement
Nov 17, 2025 – Jan 31, 2026: 205 Mt Auburn
Street residents (17 units) temporarily vacated Demolition Progresses smoothly, under budget and without incident Speaks to the quality, skills and dedication of the full team of staff and contractors working on this project
Demo & Progress Photos
13 14
Site Overview
Two separate buildings: 221 Mount Auburn Street – 9-story concrete structure with 66 units – Demolished 3-story wood and brick Bradbury Building with 14 units – Remains in place 15 6 Phases of Demolition – Timing of Phase 3 Critical Residents of the 17 units at 205 Mt Auburn temporarily evacuated, through Phase 3 16
Pre-Demo Preparation
Air quality monitors installed & approved by DEP DEP site inspections (20+ throughout demo) before and after each phase – confirm consistency with Non-Traditional Work Plan (NTWP) Fire Department inspections to ensure they were prepared to respond to an incident Temporary power for trailer and monitoring 17 units at 205 Mt Auburn temporarily evacuated, through Phase 3 17 11.2020 18
Week of 12.22.25 – Phase 1 Balconies
19
Week of 12.29.25 – Phase 2
20
Week of 12.29.25 – Phase 2
21
Week of 1.12.26 – Phase 3
22
Week of 1.19.26 – Phase 3 Complete
Residents of 205 Mt Auburn can prepare for return 23
Week of 1.26.26 – Phase 4
24
Week of 2.2.26 Phase 5
25
Week of 2.9.26 Phase 5
26
Week of 2.16.26 – Final Demolition
27
Week of 3.2.26 – Removal of Material
ZERO EXCEEDANCES
Recycled
Scrap Metal