TheCambridge Record
Agenda ItemsAwaiting Reports

AR 16-8

Asked the City Manager to confer with the Department of Public Works and the Community Development Department to work with Eversource and other power providers to plan and implement infrastructure improvements to fully support future development in Cambridge and further to confer with the appropriate departments to draft an amendment to the City’s Zoning Ordinance that would see projects needing a special permit undergo a power needs assessment as part of the permitting process

How it started
The Council asked this of the City Manager via POR 2016 #20, adopted Feb 1, 2016, sponsored by Councillor Cheung and Vice Mayor Devereux.
What happened
Apr 4, 2016 · 📨 Answered: the City Manager’s report came back as CMA 2016 #76 and the Council accepted it, answered in 63 days. (Report received and accepted)
What’s next
🚪 End of the line: request closed.
Taken upFeb 1, 2016
Report received and acceptedApr 4, 2016
Referred for reportAR 2016-8Feb 1, 2016
Administration answeredCMA 2016-76Apr 4, 2016 · answered in 63 days

The item's path through the council, every recorded step. How the request pipeline works

🏛 This item on the city's site
🗓 The meeting where this was taken up: Feb 1, 2016