TheCambridge Record
Agenda ItemsAwaiting Reports

AR 19-123

Asked the City Manager to report on the feasibility of closing some portion of Harvard Square to vehicular traffic on a select number of days during the summer of 2020 to have open market-style events

How it started
The Council asked this of the City Manager via POR 2019 #321, adopted Oct 21, 2019, sponsored by Vice Mayor Mallon and Devereux, Mayor Siddiqui, and Councillor Zondervan.
What happened
Nov 9, 2020 · 📨 Answered: the report came back and the Council accepted it. (Report received and accepted)
What’s next
🚪 End of the line: request closed.
Taken upOct 21, 2019
Report received and acceptedNov 9, 2020
Referred for reportAR 2019-123Oct 21, 2019
Awaiting answer⏳ pending2,495 days and counting

The item's path through the council, every recorded step. How the request pipeline works

🏛 This item on the city's site
🗓 The meeting where this was taken up: Oct 21, 2019