CMA 2025-283
A request for approval to seek authorization from the Massachusetts Office of the Inspector General (the “IG”) for the City to use the Construction Manager at Risk (“CMaR”) procurement and construction method (the “CMaR Method”) in connection with the DPW Salt Shed Replacement Project
Present and voting at this meeting (9)
Ayesha M. Wilson
Burhan Azeem
Cathie Zusy
E. Denise Simmons
Jivan Sobrinho-Wheeler
Marc McGovern
Patty Nolan
Paul F. Toner
Sumbul Siddiqui
Project Budget:
$6.2m estimated construction cost 30% estimated project soft costs (includes consultant fees, admin, utility fees, FF&E, site costs, & contingency) = $8.0m estimated total project cost
Project Schedule
Public Outreach
Preliminary Plan:
Initial Outreach to Abutters
October-November 2025 Questions and Comments from neighbors
City Council CMaR Approval
December 2025
Project summary
public outreach plan preliminary cost and budget
Project Website
January 2026
Pop-Up / Public Meeting – Pre-Design
Janaury 2026 Presentation of current design concept Explain project goals and intentions Overall scope and preliminary project schedule Gather feedback, questions, and concerns
Pop-Up / Public Meeting – Pre-Construction
July 2026
Construction Scope
Site Safety and logistics
Community Concerns (dust, noise, rodents, etc)